COMBINED CONTRACT ESTIMATE (COE)
The COE is generated from all uploaded estimate files. The Combined contract estimate (COE) provides detailed information for each line item in SSR, OSR, and LSR documents. The COE displays the estimate document selected in the "Estimate files" form.
Enterprise Project Structure Interface. COE
If no document is selected in the "Estimate files" form, the COE form displays a message prompting you to select an estimate document.
COE attributes include:
- activity category;
- "Document number";
- "Document code";
- "Unit code" — the code of the unit rate in the estimate standards database used to prepare the estimate (GESN, FER, TER, TSN);
- estimate line item number;
- "Name" — the document or document section name at a node, and the document line item number at the lowest hierarchy level;
- unit of measure;
- physical quantity;
- estimated costs at base and current price levels:
- "Cost with additionaly coefficients";
- "Cost";
- "Material cost" — the cost of material resources;
- "Labour cost" — the wages of the main workers;
- "Machinist cost";
- "Exploitation machine cost" — the operating cost of the machinery and equipment used;
- "Overhead cost";
- "Estimate profit cost";
- "Construction works";
- "Installation works";
- "Equipment";
- "Other";
- labor — the main workers' labor hours required for the quantity in an LSR line item, totaled at higher hierarchy levels;
- machine operator labor — the labor hours of workers operating machinery and equipment for an LSR line item, totaled at higher hierarchy levels;
- machine hours — the operating hours of machinery and equipment required for the quantity in an LSR line item, totaled at higher hierarchy levels;
- basis — the design document used to prepare the LSR.
To create a schedule template from the COE, select the schedule (1) to receive the new version and click "Create version based on сombined contract estimate" (2).
A schedule version can be created from the COE in two ways, depending on the planning mode selected in the schedule settings: simplified or resource planning.
If simplified planning is selected, the schedule creation settings dialog only requires you to select the price level for transferring cost values to the schedule version (3).
Creating a Schedule Version from the COE in Simplified Planning Mode
An activity created from an estimate line item has a default duration of five working days. Its production rate is calculated from this duration and the quantity specified in the estimate line item. Unit labor requirements are then calculated from the activity quantity and the total labor in the estimate line item, which is the sum of the main workers' labor and machine operators' labor.
If resource planning is selected, the schedule creation settings dialog also requires you to select a scenario for importing estimate data into schedule activities (4):
- "Estimate item –> schedule work and the resource plan of the same name in the WBS. Estimate item resources –> in the WBS as resources subordinate to the resource plan";
- "Estimate item – schedule work. Estimate item resources – in the WBS".
Creating a Schedule Version from the COE in Resource Planning Mode
When an estimate line item is transferred together with its resources, activity duration, production rate, and unit labor requirements are calculated in the same way as in simplified planning. The schedule's Resource planning tab displays the estimate line item as a Controlling Resource, with all resources from that line item subordinate to it. Their cost and quantity values are available for subsequent daily planning.
When only the resources of an estimate line item are transferred to an activity, the Resource planning tab displays those resources with their cost and quantity values for subsequent daily planning. The labor resource with the highest number of labor hours is assigned as the Controlling Resource. The activity duration is calculated based on that resource.
Attention! When creating a schedule version from the COE, the schedule settings on the "COST-R" tab apply.
The "Work breakdown structure" section (1) displays the structure of all documents uploaded to the project down to the document level (2). To create a new schedule work breakdown structure, click "+ Add structure" (3), enter a name (4), and use the checkboxes to select the document rows (5) to include when creating a schedule version from the COE. Enable the toggle (6) to transfer the SSR structure to the schedule. Click "Save as new structure" (7) to save a new structure, or "Save changes" (8) to save changes to the active structure. To activate a structure, click "Activate" (9).
Creating a Schedule Work Breakdown Structure
The "Schedule Work Layout" section (1) allows you to define conditions for the COE and PDC line items to include in a schedule version. To add a new layout, click "+ Add Layout" (2), enter a name (3), and select the "COE" or "PDC" tab (4). To create activities for limited and additional costs specified in the local estimate, enable the corresponding toggle (5). To apply the COE layout settings when creating a schedule from the PDC, enable "Take into account the parameters of the COE layout when creating a graph from the PDC" (6).
Click "Add Condition" (7), select a COE attribute from the drop-down list (8), and specify an operator (9) and a value (10). To add multiple attributes to a single condition, click the "AND" / "OR" operators (11). Click "Save as new layout" (12) to save a new layout, or "Save changes" (13) to save changes to the active layout. To activate a schedule work layout, click "Activate" (14).
Creating a Schedule Work Layout for the COE/PDC
COE data can be exported to .xlsx (1) using the following options: Excel (2), PLAN-R (3), "SSR/OSR template" (4), and "LSR/VOR/LS template" (5).
The Excel and PLAN-R export options include different sets of attributes. The PLAN-R export includes additional columns containing information about activities in the schedule version created from the COE. You can import this exported data back into the schedule version without losing its structure or other information required to generate the schedule correctly.
For convenience, use the button (6) to collapse or expand estimate sections to the required level.
As in "Estimate files", you can configure filters for any attribute in the COE and PDC forms by right-clicking the relevant column headers. Click "Views" (7) to configure the columns displayed in the "COE" window.
The "COE" Tab. Exporting to Excel