WORK BREAKDOWN STRUCTURE

The Work Breakdown Structure (WBS) is a hierarchy of activities to be completed within a project schedule.

In PLAN-R, the Work Breakdown Structure is a configurable hierarchical list that can contain an unlimited number of nodes in a single view. The following node types are supported:

  • Activity;
  • Start milestone;
  • Finish milestone;
  • Draft;
  • WBS node.

Activity — A task or operation performed over a defined period, with work duration, calendar duration, start, and finish as required attributes. Activity progress can range from 0 to 100. An activity can have the status "Not started", "In progress", or "Completed".

Start milestone — A task or operation with a required start attribute and no finish attribute value. It has no work or calendar duration and represents an event preceding subsequent activities or stages. Start milestone progress can be either 0 or 100. A start milestone can have the status "Not started" or "Completed".

Finish milestone — A task or operation with a required finish attribute and no start attribute value. It has no work or calendar duration and represents an event marking the completion of preceding activities or stages. Finish milestone progress can be either 0 or 100. A finish milestone can have the status "Not started" or "Completed".

Draft — A task or operation with no start or finish attribute values. Its work and calendar duration attributes may be populated or left empty. A draft is a preliminary activity whose dates have not yet been defined. Its progress can only be 0, and its only possible status is "Not started".

WBS node — A structural element (summary task) that can contain child elements, including activities, milestones, drafts, and other WBS nodes, and defines the hierarchy and structure of the schedule. Its start, finish, calendar duration, and progress are determined by the status, duration, and execution sequence of its child elements.