SCHEDULE QUALITY ANALYSIS
PLAN-R supports schedule quality analysis using the DCMA-14 methodology, which assesses 14 key schedule parameters to identify weaknesses and improve schedule reliability for project management. Open "Schedule quality" (1) in the Enterprise Project Structure to access the analysis.
To run the analysis, select a schedule (2) or one of its versions (3): Actual, Baseline, or another version. The "Schedule quality" section displays the assessment's reporting date (4). PLAN-R uses this date as the current date when calculating metrics 9, 11, 13, and 14. Dates before it are treated as past dates, and dates after it as future dates. Click the date field to open "Query parameters" (5), where you can select:
- Update date (6) — Uses the schedule version's update date.
- Current date (7) — Uses the current date when the analysis is run.
- Select date manually (8) — Uses a date specified by the user.
After selecting the reporting date, click "Execute" (9) or "Check" (10).
Schedule Quality Analysis
By default, results appear in a compact table (1). A data freshness indicator (2) shows whether the assessment was run after the latest schedule change. The indicator is green if the assessment date is later than the latest change date. It is red if the schedule has been changed without being reassessed. Click "Show details" (3) to display schedule information (4) and an expanded results table containing:
- Metric (5) — Name of the quality criterion being checked.
- Description (6) — Brief explanation of the schedule elements assessed against the criterion.
- Metric weight (7) — The metric's weight in the overall quality assessment.
- Target value (8) — The optimal value range.
- Result (9) — The value obtained from the analysis:
- % — Percentage of noncompliant elements:
(Found / Total) × 100. - Found — Number of schedule elements that do not meet the criterion.
- Total — Number of schedule elements checked against the criterion.
- % — Percentage of noncompliant elements:
- Metric quality score (10) — The score calculated as the ratio of successful metrics to their total number.
- Overall quality score (11) — An aggregate score based on individual criterion scores and their relative weights.
Left-click a value in "Found" (12) to navigate to the corresponding schedule activity. An .xlsx schedule quality assessment report is also available (13).
Schedule Quality Analysis Results
Expanded Schedule Quality Analysis Results
To view details for a criterion, click it in the table (1). A list of activities that do not meet the criterion appears at the bottom of the screen (2). Click the navigation button (3) to locate an activity in the schedule.
Criterion Details
To adapt the assessment to enterprise standards, click the analysis settings button (1). In the dialog, configure parameters for selected metrics (2), their target values (3), and weights (4). Select the corresponding checkboxes (5) to include milestones and completed activities. Click "Save" (6) to apply the settings. "Default" (7) restores the original DCMA-14 metric settings.
The configured assessment model parameters are global. They apply automatically to quality assessments of all schedules within the same space.
Configuring the Schedule Quality Assessment Model