CONSOLIDATED PROJECT SCHEDULE

PLAN-R allows you to automatically create an consolidated project schedule in which:

  • activities from different local project schedules are combined within a common target structure;
  • activities from different local project schedules are linked by technological dependencies with a Finish-to-Start relationship and zero lag, according to the schedule pairs (primary/supporting) configured for the project;
  • manually created interproject relationships are transferred to the consolidated schedule, preserving all lags and relationship types.

The consolidated project schedule is generated automatically based on the target structure code stored as an activity attribute in the different local project schedules.

Creating an Consolidated Schedule

In PLAN-R, you can create an consolidated schedule using a specified structure or without one.

To combine multiple schedules into an consolidated schedule without specifying a structure, select a node of the "Project" type (1) in the Enterprise Project Structure and open the consolidated schedule settings by clicking the corresponding button (2) in the enterprise settings panel.

register imageOpening the Consolidated Schedule Generation Settings

In the "Project schedule integration schemes" window that opens, click "Add" (1) to create a new configuration. In the "Project schedule integration scheme settings" window, enter a configuration name (2) and clear the "External WBS" checkbox (3). Click "Add Schedule" (4) to select (5) the project schedules to combine into the consolidated schedule. By default, the consolidated schedule contains only the Actual version. To create an consolidated schedule with both an Actual version and a baseline version, select the "Create baseline version" checkbox (6). When you finish configuring the settings, click "Save" (7), then click "Calculate" in the configuration selection window.

register imageCreating an Consolidated Schedule Without an External Structure

When an consolidated schedule is created without an external structure, all included schedules are combined into a single schedule and displayed in the Enterprise Project Structure as an consolidated schedule (1) with its versions (2).

register imageResult of Generating an Consolidated Schedule Without an External Structure

Before creating an consolidated schedule with a structure, prepare the schedule structure that will be used to generate it. To do this, create a schedule in the Enterprise Project Structure, then build its structure using WBS nodes.

register imageExample Schedule Structure

To prepare the schedules to be included in the consolidated schedule, complete the following steps. First, create or display a custom attribute for each schedule (1). This attribute is used to identify the activities to include in the consolidated schedule. In this attribute, enter the code (2) of the WBS node in the prepared structure where the corresponding activity should be placed. PLAN-R uses this information to identify the activities to integrate into the consolidated schedule and place them correctly in the WBS.

register imagePreparing a Schedule for Inclusion in an Consolidated Schedule

To create an consolidated schedule with an external WBS, select a node of the "Project" type (1) in the Enterprise Project Structure and open the consolidated schedule settings by clicking the corresponding button (2) in the enterprise settings panel.

An consolidated schedule with an external WBS can be created in any project in the space. It does not have to be created in the project whose schedules are being combined.

In the "Project schedule integration schemes" window that opens, click "Add" (3) to create a new configuration. Enter a name (4) for the configuration and select the "External WBS" checkbox (5). The optional "Prefix" checkbox (6) is used to identify consolidated schedule activities and prevent duplicate activity IDs from different schedules. Also select the schedule (7) whose structure will be used to generate the consolidated schedule structure. Click "Add Schedule" (8) to add one or more schedules to the consolidated schedule. Select schedules from the drop-down list of existing project schedules (9), specify the attribute containing the node code for the prepared consolidated schedule structure (10), enter an activity prefix (11), and click "Save" (12). After saving the settings, click "Calculate" (13).

register imageConfiguring an Consolidated Schedule

After the calculation is completed successfully, a new project schedule (1) appears in the Enterprise Project Structure. Its name matches the name of the consolidated schedule configuration used for the calculation. An consolidated schedule version (2) also appears with the update date specified during the calculation.

register imageConsolidated Schedule in the Enterprise Project Structure

When you open the consolidated schedule, you can see that activities from other schedules have been placed in the structure according to the codes entered in the custom attribute. A prefix (1) has also been added to each activity in the consolidated schedule, making it easier to identify its source and organize the data display.

register imageConsolidated Schedule Work Breakdown Structure

Updating an Consolidated Schedule

If activities in a schedule included in the consolidated schedule are modified, update the consolidated schedule. To do this, select a node of the "Project" type (1) in the Enterprise Project Structure and open the consolidated schedule settings by clicking the corresponding button (2) in the enterprise settings panel. In the "Project schedule integration schemes" window that opens, click "Calculate" (3) for the saved configuration used by the consolidated schedule. The consolidated schedule will be recalculated using the latest data.

register imageUpdating an Consolidated Schedule

Copying Consolidated Schedule Settings

PLAN-R allows you to duplicate consolidated schedule settings within the selected project or copy them to create new configurations in other projects.

To duplicate consolidated schedule settings, select a node of the "Project" type (1) in the Enterprise Project Structure and click "Consolidated schedule" (2). In the "Project schedule integration schemes" window, click "Duplicate" (3) for the required configuration. A new configuration appears in the list of project schedule integration schemes. You can edit it in the "Project schedule integration scheme settings" window. After making changes, click "Save" (4) and "Calculate" (5) to save and apply them.

register imageDuplicating Consolidated Schedule Settings

To copy consolidated schedule settings to another project, select a node of the "Project" type (1) and click "Consolidated schedule" (2). In the "Project schedule integration schemes" window, click "Copy settings" (3) for the required configuration.

register imageCopying Consolidated Schedule Settings to Another Project (1)

Next, return to the Enterprise Project Structure (1), select the required node of the "Project" type (2), and click "Consolidated schedule" (3). In the "Project schedule integration schemes" window, click "Paste saved settings" (4). The "Project schedule integration scheme settings" window opens with the copied settings, which you can edit. If the data (schedules and attributes) referenced by the settings is unavailable when you paste them into a new consolidated schedule in another project, the settings window displays the "Invalid Data" warning (5).

To save the new configuration, click "Save" (6).

register imageCopying Consolidated Schedule Settings to Another Project (2)

To apply the settings and create the consolidated schedule, click "Calculate" (1). An consolidated schedule (3) created using the consolidated schedule settings from another project appears under the selected project (2) in the Enterprise Project Structure.

register imageCreating an Consolidated Schedule Using Consolidated Schedule Settings from Another Project