PROJECT WINDOW INTERFACE
PLAN-R allows you to customize the schedule interface by displaying multiple windows simultaneously. To do this, use the "Project window" tab (1).
Project Window Interface
Creating a New Tab in the Project Window Interface
To create a new tab in the "Project window", open the tab selection drop-down (1) and click the + icon (2) in the upper-left corner. The new tab creation window will open. Enter a tab name (3), select a schedule (4), and select its version (5). This window also offers predefined templates (6) with specific sets of windows. Alternatively, you can add an empty tab and create your own layout for working with the schedule.
You can move the newly created tab forward or backward relative to the other tabs.
Adding a New Tab in the Project Window Interface
To rename a tab, open the tab selection drop-down (1), right-click the required tab, and select "Rename" (2). In the window that opens, enter the tab name (3) and click "Rename" (4).
Renaming a Tab in the Project Window Interface
Click "Create a new template based on the tab" (1) to save the configured tab as a project screen template.
Creating a Custom Project Screen Template
When you open the new tab creation window (1), you can edit (2) or delete (3) custom project screen templates.
Editing or Deleting a Custom Project Screen Template
Working with Windows in a New Tab
The top of the tab shows which schedule version the current set of windows is open for (1).
To add a window, right-click an empty area. A menu appears with the following windows available to add (2):
- Activity card (see "Activity Card");
- Activity links (see "Configuring Relationships Between Schedule Activities");
- Related schedules (see "Project Schedule Integration");
- Directories (see "Directories");
- Resource planning (see "Planning in PLAN-R");
- Checklists (see "Checklists");
- Photos / Documents (see "Photo Documentation and Documents");
- Assignments (see "Requests and Assignments");
- BIM (see "BIM-R Information Modeling");
- WBS (see "Project Schedules");
- Project Screen (see "Project Screens");
- Resources (see "Resource Directory");
- Multiwidget (see "Project Schedules");
- COST-R (see "COST-R Cost Estimate Data"):
- Estimate files;
- Combined contract estimate;
- Enlarged rules;
- Work types;
- Estimated contract scope;
- Mapping directory of measure units;
- Detailed position information;
- Detailed resource information;
- Assigned rates.
The Multiwidget contains the windows displayed in the lower part of the schedule interface in the "Schedule" section: Activity card, Activity links, Related schedules, Directories, Resource planning, Checklists, Photos / Documents, and Assignments.
Adding New Windows to a Tab
You can rearrange windows by dragging them to the required positions on the tab.
When working with windows, PLAN-R allows you to:
- automatically adjust the window size to fit the other windows (1);
- collapse the window (2);
- maximize the window to fill the screen (3);
- close the window (4).
To resize a window, drag its lower-right corner. The size will change if the resized window does not overlap another window. Otherwise, its size will remain unchanged.
Tab with Windows in the Project Window Interface