ANNEX 2. SCHEDULE CALCULATION ALGORITHMS FOR DIFFERENT SCENARIOS

The PLAN-R construction project management platform allows you to assign different scenarios to activities, start milestones, and finish milestones using the "Scenario type" attribute. These scenarios determine start, finish, and completion percentage (progress) at the specified calculation date:

By duration:

  • 1.1. Estimated % - units/time by original duration;
    1.2. Estimated % - units/time by baseline duration;
    1.3. Estimated % - units/time by actual duration;
    1.4. Fixed deadlines;
    1.5. Estimated % - fixed units/time by remaining duration;
    1.6. Fixed deadlines and % complete.

By total physical volume:

  • 2.1. By physical volume units/time;
    2.2. Physical volume - units/time by actual duration;
    2.3. Physical volume - units/time by original duration;
    2.4. Physical volume - units/time by baseline duration;
    2.5 Physical volume - fixed units/time by remaining duration.

By daily physical volumes:

  • 3.1. By physical volume units/time, start/finish by daily actuals;
    3.2. Physical volume - units/time by actual duration, start/finish by daily actuals;
    3.3. Physical volume - units/time by original duration, start/finish by daily actuals;
    3.4. Physical volume - units/time by baseline duration, start/finish by daily actuals;
    3.5 Physical volume - fixed units/time by remaining duration, start/finish by daily actuals.

By total labor units:

  • 4.1. Labor units - units/time by actual duration;
    4.2. Labor units - units/time by original duration;
    4.3. Labor units - units/time by baseline duration;
    4.4 Labor units - fixed units/time by remaining duration.

By daily labor units:

  • 5.1 Labor units - units/time by actual duration, start/finish by daily actuals;
    5.2 Labor units - units/time by original duration, start/finish by daily actuals;
    5.3 Labor units - units/time by baseline duration, start/finish by daily actuals;
    5.4 Labor units - fixed units/time by remaining duration, start/finish by daily actuals.

By total cost:

  • 6.1. Cost - units/time by actual duration;
    6.2. Cost - units/time by original duration;
    6.3. Cost - units/time by baseline duration.

Activities and milestones with no "Scenario type" value use the scenario selected in the settings when the schedule is calculated. A scenario assigned directly to an activity takes precedence over the scenario selected in the schedule calculation settings window.

During schedule calculation, the scenario can affect the following activity parameters, and some milestone parameters, based on the specified calculation date (DD):

  • Start (S)
  • Finish (F)
  • Progress (%)
  • Status
  • Work duration (WD)
  • Original duration (BD)
  • Actual work duration (AWD)
  • Remaining work duration (RWD)
  • Calendar duration (D)
  • Calendar (Cal)
  • Constraints
  • "In range" mode (Earlier, Later, Empty, Stretch)
  • First actual date (FFD)
  • Last actual date (LFD)
  • Schedule calculation date (DD)

When no constraints are assigned and "In range" is set to "Earlier", manually changing these activity parameters synchronizes their values automatically according to the following rules:

    % = (AWD / WD) \* 100%
    RWD = WD – AWD
    D = WD adjusted for Cal
    F = S + D – 1

The following parameters apply to start and finish milestones:

    Start (S) – for start milestones
    Finish (F) – for finish milestones
    Progress (%) – 0 or 100.

Schedule version calculation consists of two stages:

  • Calculating activity/milestone dates from completion %, activity dates, and calculation date (DD);
  • Calculating activity/milestone dates from dependencies (predecessors);
  • Calculating activity float (free and total);
  • Shifting activities with "In range" set to "Later" or "Stretch";
  • Identifying critical path activities.

STAGE 1

CALCULATING ACTIVITY/MILESTONE DATES FROM COMPLETION %, ACTIVITY DATES, AND THE SCHEDULE CALCULATION DATE (DD)

The algorithms for calculating activity time parameters at this stage depend on the scenario assigned to the activity or milestone. The algorithms below assume no assigned constraints, "In range" set to "Earlier", and "Not started" status with progress from 1% to 99%. Activities with "In progress" status and 0% progress are calculated in the same way as activities with progress from 1% to 99%.

SCENARIO 1.1: Estimated % - units/time by original duration

In this scenario, the planned finish of started activities is determined from current progress (duration completion percentage) and start date. The original execution rate is calculated from original duration (BD, "Original duration"), and remaining duration is calculated from that rate. If original duration is missing, the default scenario is applied: scenario 1.3, "Estimated % - units/time by actual duration".

Activity time parameter calculation algorithm:

  • If % = 0, then

if S > DD, then S = DD. Then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1;

if S <= DD, then S = DD, then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1.

  • If % = 100, then

if S < DD and F > DD, then F = DD - 1, WD = (DD – S)*Cal, AWD = WD, RWD = 0, D = F – S + 1;

if S < DD and F <= DD, then activity time parameters remain unchanged;

if S >= DD, then RWD and AWD remain unchanged, S = (DD – AWD)*Cal, F = (DD + RWD – 1)*Cal, D = F – S + 1, WD = AWD + RWD.

  • If 0 < % < 100, then

if DD > S, then F = DD + (BD*((100%-%)/100%) – 1)*Cal, AWD = (DD – S)*Cal, RWD = (F – DD + 1)*Cal, WD = AWD + RWD, D = F – S + 1;

if DD <= S, then WD, AWD and RWD remain unchanged, S = (DD – AWD)*Cal, F = (DD + RWD – 1)*Cal, D = F – S + 1.

Start milestone time parameter calculation algorithm:

  • If % = 0, then if S > DD, then S = DD; if S <= DD, then S = DD.
  • If % = 100, then if S < DD, then start milestone time parameters remain unchanged; if S >= DD, then S = DD – 1.

Finish milestone time parameter calculation algorithm:

  • If % = 0, then if F > DD, then F = DD; if F <= DD, then F = DD.
  • If % = 100, then if F < DD, then finish milestone time parameters remain unchanged; if F >= DD, then F = DD – 1.

SCENARIO 1.2: Estimated % - units/time by baseline duration

In this scenario, the planned finish of started activities is determined from current progress (duration completion percentage) and start date. The baseline execution rate is calculated from activity duration in the baseline schedule version (TD), and remaining duration is calculated from that rate. If the activity is missing from the baseline version, the default scenario is applied: scenario 1.3, "Estimated % - units/time by actual duration".

Activity time parameter calculation algorithm:

  • If % = 0, then

if S > DD, then S = DD. Then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1;

if S <= DD, then S = DD, then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1.

  • If % = 100, then

if S < DD and F > DD, then F = DD - 1, WD = (DD – S)*Cal, AWD = WD, RWD = 0, D = F – S + 1;

if S < DD and F <= DD, then activity time parameters remain unchanged;

if S >= DD, then RWD and AWD remain unchanged, S = (DD – AWD)*Cal, F = (DD + RWD – 1)*Cal, D = F – S + 1, WD = AWD + RWD.

  • If 0 < % < 100, then

if DD > S, then F = DD + (TD*((100%-%)/100%) - 1)*Cal, AWD = (DD – S)*Cal, RWD = (F – DD + 1)*Cal, WD = AWD + RWD, D = F – S + 1;

if DD <= S, then WD, AWD and RWD remain unchanged, S = (DD – AWD)*Cal, F = (DD + RWD – 1)*Cal, D = F – S + 1.

Start milestone time parameter calculation algorithm:

  • If % = 0, then if S > DD, then S = DD. if S <= DD, then S = DD.
  • If % = 100, then if S < DD, then start milestone time parameters remain unchanged; if S >= DD, then S = DD – 1.

Finish milestone time parameter calculation algorithm:

  • If % = 0, then if F > DD, then F = DD; if F <= DD, then F = DD.
  • If % = 100, then if F < DD, then finish milestone time parameters remain unchanged; if F >= DD, then F = DD – 1.

SCENARIO 1.3: Estimated % - units/time by actual duration

In this scenario, the planned finish of started activities is determined from current progress (duration completion percentage) and start date. The actual execution rate is calculated, and remaining duration is calculated from that rate.

Activity time parameter calculation algorithm:

  • If % = 0, then

if S > DD, then S = DD. Then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1;

if S <= DD, then S = DD, then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1.

  • If % = 100, then

if S < DD and F > DD, then F = DD - 1, WD = (DD – S)*Cal, AWD = WD, RWD = 0, D = F – S + 1;

if S < DD and F <= DD, then activity time parameters remain unchanged;

if S >= DD, then RWD and AWD remain unchanged, S = (DD – AWD)*Cal, F = (DD + RWD – 1)*Cal, D = F – S + 1, WD = AWD + RWD.

  • If 0 < % < 100, then if DD > S, then F = (DD + (100-%)/(%/(DD – S)) – 1)*Cal, AWD = (DD – S)*Cal, RWD = (F – DD + 1)*Cal, WD = AWD + RWD, D =F – S + 1;

if DD <= S, then WD, AWD and RWD remain unchanged, S = (DD – AWD)*Cal, F = (DD + RWD – 1)*Cal, D = F – S + 1.

Start milestone time parameter calculation algorithm:

  • If % = 0, then

if S > DD, then S = DD;

if S <= DD, then S = DD.

  • If % = 100, then

if S < DD, then start milestone time parameters remain unchanged;

if S >= DD, then S = DD – 1.

Finish milestone time parameter calculation algorithm:

  • If % = 0, then

if F > DD, then F = DD;

if F <= DD, then F = DD.

  • If % = 100, then

if F < DD, then finish milestone time parameters remain unchanged;

if F >= DD, then F = DD – 1.

SCENARIO 1.4: Fixed deadlines

In this scenario, progress (duration completion percentage for activities and milestones), actual work duration (AWD), and remaining work duration (RWD) are determined from the current start and finish dates without changing those dates.

Activity time parameter calculation algorithm:

  • if S > DD, then % = 0, AWD = 0, RWD = WD.
  • if S <= DD and F >= DD, then % = ((DD – S)/(F – S + 1))*100%, AWD = (DD – S)*Cal; RWD = WD – AWD.
  • if F < DD, then % = 100, AWD = WD; RWD = 0.

Start milestone time parameter calculation algorithm:

  • if S >= DD, then % = 0.
  • if S < DD, then % = 100.

Finish milestone time parameter calculation algorithm:

  • if F >= DD, then % = 0.
  • if F < DD, then % = 100

SCENARIO 1.5: Estimated % - fixed units/time by remaining duration

For activities in progress, this scenario keeps finish unchanged regardless of execution rate, provided the update date is earlier than finish. If the update date is on or after finish, one day is added to finish. Start is calculated from relationships, the update date, and assigned constraints.

Activity time parameter calculation algorithm:

  • If % = 0, then

if S > DD, then S = DD. Then AWD = 0, RWD = BD, F = (S + BD – 1)*Cal, D = F – S + 1;

if S <= DD, then S = DD. Then AWD = 0, RWD = BD, F = (S + BD – 1)*Cal, D = F – S + 1.

  • If % = 100, then

if S > DD, then RWD = 0. Then AWD = BD, S = (DD – BD)*Cal, F = (DD – 1)*Cal, D = F – S + 1, WD = AWD + RWD;

if S < DD & F > DD, then F = DD – 1, S = (DD – BD)*Cal, AWD = BD, RWD = 0, D = F – S + 1;

if S < DD & F <= DD, then activity time parameters remain unchanged.

  • If 0 < % < 100, then

if S > DD, S = CONST, F = CONST, AWD = CONST, RWD = CONST;

if S < DD & F > DD, S = CONST, F = CONST, AWD = CONST, RWD = CONST;

if S < DD & F <= DD, then S = CONST, F = DD + 1, D = F – S + 1, WD = RWD + AWD, AWD = (DD – S)*Cal, RWD = (F – DD + 1)*Cal.

SCENARIO 1.6: Fixed deadlines and % complete

In this scenario, progress (duration completion percentage for activities and milestones), start and finish dates, and actual work, remaining work, work, and calendar durations do not change during schedule calculation.

SCENARIO 2.1: By physical volume units/time

In this scenario, the planned finish of started activities is determined from current progress (physical quantity completion percentage), start date, and physical quantity production rate (I, "Units/time"). Remaining duration is calculated from that rate. If production rate is missing, scenario 2.2, "Physical volume - units/time by actual duration", is applied.

Activity time parameter calculation algorithm:

  • If PV completion % = 0, then

if S > DD, then S = DD. Then AWD = 0, RWD = WD, WD = (Planned PV /I), F = (S + WD – 1)*Cal, D = F – S + 1;

if S <= DD, then S = DD, then AWD = 0, RWD = WD, WD = (Planned PV /I), F = (S + WD – 1)*Cal, D = F – S + 1.

  • If PV completion % = 100, then

if S < DD and F > DD, then F = DD - 1, WD = (DD – S)*Cal, AWD = WD, RWD = 0, D = F – S + 1;

if S < DD and F <= DD, then activity time parameters remain unchanged;

if S >= DD, then RWD and AWD remain unchanged, S = (DD – AWD)*Cal, F = (DD + RWD – 1)*Cal, D = F – S + 1, WD = AWD + RWD.

  • If 0 < PV completion % < 100, then

if DD > S, then F = DD + ((Planned PV – Actual PV) /I – 1)*Cal, AWD = (DD – S)*Cal, RWD = (F – DD + 1)*Cal, WD = AWD + RWD, D = F – S + 1;

if DD <= S, then WD, AWD and RWD remain unchanged, S = DD - (Actual PV /I)*Cal, F = DD + ((Planned PV – Actual PV) /I – 1)*Cal, D = F – S + 1.

Start milestone time parameter calculation algorithm:

  • If PV completion % = 0, then if S > DD, then S = DD; if S <= DD, then S = DD.
  • If PV completion % = 100, then if S < DD, then start milestone time parameters remain unchanged; if S >= DD, then S = DD – 1.

Finish milestone time parameter calculation algorithm:

  • If PV completion % = 0, then if F > DD, then F = DD; if F <= DD, then F = DD.
  • If PV completion % = 100, then if F < DD, then finish milestone time parameters remain unchanged; if F >= DD, then F = DD – 1.

SCENARIO 2.2: Physical volume - units/time by actual duration

In this scenario, the planned finish of started activities is determined from current physical quantity completion percentage and start date. The actual physical quantity production rate is calculated, and remaining duration is calculated from that rate.

Activity time parameter calculation algorithm:

  • If PV completion % = 0, then

if S > DD, then S = DD. Then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1;

if S <= DD, then S = DD, then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1.

  • If PV completion % = 100, then

if S < DD and F > DD, then F = DD - 1, WD = (DD – S)*Cal, AWD = WD, RWD = 0, D = F – S + 1;

if S < DD and F <= DD, then activity time parameters remain unchanged;

if S >= DD, then RWD and AWD remain unchanged, S = (DD – AWD)*Cal, F = (DD + RWD – 1)*Cal, D = F – S + 1, WD = AWD + RWD.

  • If 0 < PV completion % < 100, then

if DD > S, then F = (DD + (100-%)/(PV completion %/(DD – S)) – 1)*Cal, AWD = (DD – S)*Cal, RWD = (F – DD + 1)*Cal, WD = AWD + RWD, D = F – S + 1;

if DD <= S, then WD, AWD and RWD remain unchanged, S = (DD – AWD)*Cal, F = (DD + RWD – 1)*Cal, D = F – S + 1.

Start milestone time parameter calculation algorithm:

  • If PV completion % = 0, then if S > DD, then S = DD; if S <= DD, then S = DD.
  • If PV completion % = 100, then if S < DD, then start milestone time parameters remain unchanged; if S >= DD, then S = DD – 1.

Finish milestone time parameter calculation algorithm:

  • If PV completion % = 0, then if F > DD, then F = DD; if F <= DD, then F = DD.
  • If PV completion % = 100, then if F < DD, then finish milestone time parameters remain unchanged; if F >= DD, then F = DD – 1.

SCENARIO 2.3: Physical volume - units/time by original duration

In this scenario, the planned finish of started activities is determined from current physical quantity completion percentage and start date. The original execution rate is calculated from original duration (BD, "Original duration"), and remaining duration is calculated from that rate. If original duration is missing, scenario 2.2, "Physical volume - units/time by actual duration", is applied.

Activity time parameter calculation algorithm:

  • If PV completion % = 0, then

if S > DD, then S = DD. Then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1;

if S <= DD, then S = DD, then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1.

  • If PV completion % = 100, then

if S < DD and F > DD, then F = DD - 1, WD = (DD – S)*Cal, AWD = WD, RWD = 0, D = F – S + 1;

if S < DD and F <= DD, then activity time parameters remain unchanged;

if S >= DD, then RWD and AWD remain unchanged, S = (DD – AWD)*Cal, F = (DD + RWD – 1)*Cal, D = F – S + 1, WD = AWD + RWD.

  • If 0 < PV completion % < 100, then

if DD > S, then F = DD + (BD*((100%-PV completion %)/100%) – 1)*Cal, AWD = (DD – S)*Cal, RWD = (F – DD + 1)*Cal, WD = AWD + RWD, D = F – S + 1;

if DD <= S, then WD, AWD and RWD remain unchanged, S = (DD – AWD)*Cal, F = (DD + RWD – 1)*Cal, D = F – S + 1.

Start milestone time parameter calculation algorithm:

  • If PV completion % = 0, then

if S > DD, then S = DD; if S <= DD, then S = DD.

  • If PV completion % = 100, then

if S < DD, then start milestone time parameters remain unchanged; if S >= DD, then S = DD – 1.

Finish milestone time parameter calculation algorithm:

  • If PV completion % = 0, then if F > DD, then F = DD; if F <= DD, then F = DD.
  • If PV completion % = 100, then if F < DD, then finish milestone time parameters remain unchanged; if F >= DD, then F = DD – 1.

SCENARIO 2.4: Physical volume - units/time by baseline duration

In this scenario, the planned finish of started activities is determined from current physical quantity completion percentage and start date. The baseline execution rate is calculated from activity duration in the baseline schedule version (TD), and remaining duration is calculated from that rate. If the activity is missing from the baseline version, the default scenario is applied: scenario 2.2, "Physical volume - units/time by actual duration".

Activity time parameter calculation algorithm:

  • If PV completion % = 0, then

if S > DD, then S = DD. Then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1;

if S <= DD, then S = DD, then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1.

  • If PV completion % = 100, then

if S < DD and F > DD, then F = DD - 1, WD = (DD – S)*Cal, AWD = WD, RWD = 0, D = F – S + 1;

if S < DD and F <= DD, then activity time parameters remain unchanged;

if S >= DD, then RWD and AWD remain unchanged, S = (DD – AWD)*Cal, F = (DD + RWD – 1)*Cal, D = F – S + 1, WD = AWD + RWD.

  • If 0 < PV completion % < 100, then

if DD > S, then F = DD + (TD*((100%-PV completion %)/100%) - 1)*Cal, AWD = (DD – S)*Cal, RWD = (F – DD + 1)*Cal, WD = AWD + RWD, D = F – S + 1;

if DD <= S, then WD, AWD and RWD remain unchanged, S = (DD – AWD)*Cal, F = (DD + RWD – 1)*Cal, D = F – S + 1.

Start milestone time parameter calculation algorithm:

  • If PV completion % = 0, then if S > DD, then S = DD; if S <= DD, then S = DD.
  • If PV completion % = 100, then if S < DD, then start milestone time parameters remain unchanged; if S >= DD, then S = DD – 1.

Finish milestone time parameter calculation algorithm:

SCENARIO 2.5: Physical volume - fixed units/time by remaining duration

For activities in progress, this scenario keeps finish unchanged regardless of the physical quantity production rate, provided the update date is earlier than finish. If the update date is on or after finish, one day is added to finish. Start is calculated from relationships, the update date, and assigned constraints.

Activity time parameter calculation algorithm:

  • If PV completion % = 0, then

if S > DD, then S = DD. Then AWD = 0, RWD = BD, F = (S + BD – 1)*Cal, D = F – S + 1;

if S <= DD, then S = DD, then AWD = 0, RWD = BD, F = (S + BD – 1)*Cal, D = F – S + 1.

  • If PV completion % = 100, then

if FFD > DD, then S = FFD, F = LFD, D = F – S + 1, BD = CONST, WD = (F – S + 1)*Cal, AWD = WD, RWD = 0;

if FFD < DD & LFD > DD, then S = FFD, F = LFD, D = F – S + 1, BD = CONST, WD = (F – S + 1)*Cal, AWD = WD, RWD = 0;

if FFD < DD & LFD <= DD, then S = FFD, F = LFD, D = F – S + 1, BD = CONST, WD = (F – S + 1)*Cal, AWD = WD, RWD = 0.

  • If 0 < PV completion % < 100%, then

if FFD > DD, then S = FFD, F = (S + BD - 1)*Cal, D = F – S + 1, WD = (F – S + 1)*Cal, AWD = 0, RWD = WD;

if FFD < DD & BD – (DD – FFD) > 0, then S = FFD, F = DD + (BD – (DD – FFD))*Cal (provided F >= LFD, if LFD > F, then F = LFD), AWD = DD – FFD, RWD = BD – AWD, WD = RWD + AWD, D = F – S + 1;

if FFD < DD & BD – (DD – FFD) < 0, then S = FFD, F = (DD + 1)* Cal, AWD = DD – FFD, RWD = 1, WD = RWD + AWD, D = F – FFD + 1.

SCENARIO 3.1: By physical volume units/time, start/finish by daily actuals

In this scenario, the planned finish of started activities is determined from current physical quantity completion percentage, start date, and physical quantity production rate (I, "Units/time"). Remaining duration is calculated from that rate. If production rate is missing, scenario 2.2, "Physical volume - units/time by actual duration", is applied. Activities start automatically based on the entered daily physical quantity plan and finish automatically when daily actual physical quantities fulfill the total plan.

Activity time parameter calculation algorithm:

  • If PV completion % = 0, then

if S >= DD, then S = DD. Then AWD = 0, RWD = WD, WD = (Planned PV /I), F = (S + WD – 1)*Cal, D = F – S + 1;

if S < DD, then S = DD, then AWD = 0, RWD = WD, WD = (Planned PV /I), F = (S + WD – 1)*Cal, D = F – S + 1.

  • If PV completion % = 100, then

if S = FFD, where FFD – first actual date, F = LFD, where LFD – last actual date. RWD = 0, AWD = WD, WD = (F – S + 1) * Cal.

  • If 0 < PV completion % < 100, then

If S <= DD, then S = FFD, where FFD – first actual date, F = DD + ((Planned PV – Actual PV) /I – 1)*Cal, AWD = (DD – S)*Cal, RWD = (F – DD + 1)*Cal, WD = RWD, D = F – S + 1;

if S >= DD, then S = FFD, where FFD – first actual date, WD remains unchanged, RWD = WD*(100 - %), AWD = WD = RWD.

Start milestone time parameter calculation algorithm:

  • If PV completion % = 0, then if S >= DD, then S = DD; if S < DD, then S = DD.
  • If PV completion % = 100, then if S < DD, then start milestone time parameters remain unchanged; if S >= DD, then S = DD – 1.

Finish milestone time parameter calculation algorithm:

  • If PV completion % = 0, then if F >= DD, then F = DD; if F < DD, then F = DD.
  • If PV completion % = 100, then if F < DD, then finish milestone time parameters remain unchanged; if F >= DD, then F = DD – 1.

SCENARIO 3.2: Physical volume - units/time by actual duration, start/finish by daily actuals

In this scenario, the planned finish of started activities is determined from current physical quantity completion percentage and start date. The actual physical quantity production rate is calculated, and remaining duration is calculated from that rate. Activities start automatically based on the entered daily physical quantity plan and finish automatically when daily actual physical quantities fulfill the total plan.

Activity time parameter calculation algorithm:

  • If PV completion % = 0, then

if S >= DD, then S = DD. Then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1;

if S < DD, then S = DD, then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1.

  • If PV completion % = 100, then

if S = FFD, where FFD – first actual date, F = LFD, where LFD – last actual date. RWD = 0, AWD = WD, WD = (F – S + 1) * Cal.

  • If 0 < PV completion % < 100, then

If S < DD, then S = FFD, where FFD – first actual date, F = (DD + (100-%)/(PV completion %/(DD – S)) – 1)*Cal, AWD = (DD – S)*Cal, RWD = (F – DD + 1)*Cal, WD = RWD, D = F – S + 1;

if S >= DD, then S = FFD, where FFD – first actual date, WD remains unchanged, RWD = WD*(100 - PV completion %), AWD = WD - RWD

Start milestone time parameter calculation algorithm:

  • If PV completion % = 0, then if S >= DD, then S = DD; if S < DD, then S = DD.
  • If PV completion % = 100, then if S < DD, then start milestone time parameters remain unchanged; if S >= DD, then S = DD – 1.

Finish milestone time parameter calculation algorithm:

  • If PV completion % = 0, then if F >= DD, then F = DD; if F < DD, then F = DD.
  • If PV completion % = 100, then if F < DD, then finish milestone time parameters remain unchanged; if F >= DD, then F = DD – 1.

SCENARIO 3.3: Physical volume - units/time by original duration, start/finish by daily actuals

In this scenario, the planned finish of started activities is determined from current physical quantity completion percentage and start date. The original execution rate is calculated from original duration (BD, "Original duration"), and remaining duration is calculated from that rate. If original duration is missing, scenario 2.2, "Physical volume - units/time by actual duration", is applied. Activities start automatically based on the entered daily physical quantity plan and finish automatically when daily actual physical quantities fulfill the total plan.

Activity time parameter calculation algorithm:

  • If PV completion % = 0, then

S = DD. Then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1;

  • If PV completion % = 100, then

if S = FFD, where FFD – first actual date, F = LFD, where LFD – last actual date. RWD = 0, AWD = WD, WD = (F – S + 1) * Cal.

  • If 0 < PV completion % < 100, then

If S < DD, then S = FFD, where FFD – first actual date, F = DD + (BD*((100%-PV completion %)/100%) – 1)*Cal, AWD = (DD – S)*Cal, RWD = (F – DD + 1)*Cal, WD = RWD + AWD, D = F – S + 1;

if S >= DD, then S = FFD, where FFD – first actual date, WD remains unchanged, RWD = BD*(100 - %), AWD = WD - RWD

Start milestone time parameter calculation algorithm:

  • If PV completion % = 0, then if S >= DD, then S = DD; if S < DD, then S = DD.
  • If PV completion % = 100, then if S < DD, then start milestone time parameters remain unchanged; if S >= DD, then S = DD – 1.

Finish milestone time parameter calculation algorithm:

  • If PV completion % = 0, then if F >= DD, then F = DD; if F < DD, then F = DD.
  • If PV completion % = 100, then if F < DD, then finish milestone time parameters remain unchanged; if F >= DD, then F = DD – 1.

SCENARIO 3.4: Physical volume - units/time by baseline duration, start/finish by daily actuals

In this scenario, the planned finish of started activities is determined from current physical quantity completion percentage and start date. The baseline execution rate is calculated from activity duration in the baseline schedule version (TD), and remaining duration is calculated from that rate. If the activity is missing from the baseline version, the default scenario is applied: scenario 2.2, "Physical volume - units/time by actual duration". Activities start automatically based on the entered daily physical quantity plan and finish automatically when daily actual physical quantities fulfill the total plan.

Activity time parameter calculation algorithm:

  • If PV completion % = 0, then

if S >= DD, then S = DD. Then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1;

if S < DD, then S = DD, then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1.

  • If PV completion % = 100, then

if S = FFD, where FFD – first actual date, F = LFD, where LFD – last actual date. RWD = 0, AWD = WD, WD = (F – S + 1) * Cal.

  • If 0 < PV completion % < 100, then

If S < DD, then S = FFD, where FFD – first actual date, F = DD + (TD*((100%-PV completion %)/100%) – 1)*Cal, AWD = (DD – S)*Cal, RWD = (F – DD + 1)*Cal, RWD = WD - AWD, D = F – S + 1;

if S >= DD, then S = FFD, where FFD – first actual date, WD remains unchanged, RWD = TD*(100 - PV completion %), AWD = WD - RWD

Start milestone time parameter calculation algorithm:

  • If PV completion % = 0, then if S >= DD, then S = DD; if S < DD, then S = DD.
  • If PV completion % = 100, then if S < DD, then start milestone time parameters remain unchanged; if S >= DD, then S = DD – 1.

Finish milestone time parameter calculation algorithm:

  • If PV completion % = 0, then if F >= DD, then F = DD; if F < DD, then F = DD.
  • If PV completion % = 100, then if F < DD, then finish milestone time parameters remain unchanged; if F >= DD, then F = DD – 1.

SCENARIO 3.5: Physical volume - fixed units/time by remaining duration, start/finish by daily actuals

When total planned and actual physical quantities have been entered, this scenario sets start to the earliest actual entry date. Finish remains unchanged regardless of actual quantity, provided the update date is earlier than finish. If the update date is on or after finish, one day is added to finish. When Progress = 100, finish is set to the latest actual entry date.

Activity time parameter calculation algorithm:

  • If PV completion % = 0, then

if S > DD, then S = DD. Then AWD = 0, RWD = BD, F = (S + BD – 1)*Cal, D = F – S + 1;

if S <= DD, then S = DD, then AWD = 0, RWD = BD, F = (S + BD – 1)*Cal, D = F – S + 1.

  • If PV completion % = 100, then

if FFD > DD, then S = FFD, F = LFD, D = F – S + 1, BD = CONST, WD = (F – S + 1)*Cal, AWD = WD, RWD = 0;

if FFD < DD & LFD > DD, then S = FFD, F = LFD, D = F – S + 1, BD = CONST, WD = (F – S + 1)*Cal, AWD = WD, RWD = 0;

if FFD < DD & LFD <= DD, then S = FFD, F = LFD, D = F – S + 1, BD = CONST, WD = (F – S + 1)*Cal, AWD = WD, RWD = 0.

  • If 0 < PV completion % < 100%, then

if FFD > DD, then S = FFD, F = (S + BD - 1)*Cal, D = F – S + 1, WD = (F – S + 1)*Cal, AWD = 0, RWD = WD;

if FFD < DD & BD – (DD – FFD) > 0, then S = FFD, F = DD + (BD – (DD – FFD))*Cal (provided F >= LFD, if LFD > F, then F = LFD), AWD = DD – FFD, RWD = BD – AWD, WD = RWD + AWD, D = F – S + 1;

if FFD < DD & BD – (DD – FFD) < 0, then S = FFD, F = (DD + 1)* Cal, AWD = DD – FFD, RWD = 1, WD = RWD + AWD, D = F – FFD + 1.

SCENARIO 4.1: Labor units - units/time by actual duration

In this scenario, the planned finish of started activities is determined from current labor completion percentage and start date. The actual labor usage rate is calculated, and remaining duration is calculated from that rate.

Activity time parameter calculation algorithm:

  • If Labor completion % = 0, then

if S > DD, then S = DD. Then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1;

if S <= DD, then S = DD, then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1.

  • If Labor completion % = 100, then

if S < DD and F > DD, then F = DD - 1, WD = (DD – S)*Cal, AWD = WD, RWD = 0, D = F – S + 1;

if S < DD and F <= DD, then activity time parameters remain unchanged;

if S >= DD, then RWD and AWD remain unchanged, S = (DD – AWD)*Cal, F = (DD + RWD – 1)*Cal, D = F – S + 1, WD = AWD + RWD.

  • If 0 < Labor completion % < 100, then

if DD > S, then F = (DD + (100-%)/(Labor completion %/(DD – S)) – 1)*Cal, AWD = (DD – S)*Cal, RWD = (F – DD + 1)*Cal, WD = AWD + RWD, D =F – S + 1; if DD <= S, then WD, AWD and RWD remain unchanged, S = (DD – AWD)*Cal, F = (DD + RWD – 1)*Cal, D = F – S + 1.

Start milestone time parameter calculation algorithm:

  • If Labor completion % = 0, then if S > DD, then S = DD; if S <= DD, then S = DD.
  • If Labor completion % = 100, then if S < DD, then start milestone time parameters remain unchanged; if S >= DD, then S = DD – 1.

Finish milestone time parameter calculation algorithm:

  • If Labor completion % = 0, then if F > DD, then F = DD; if F <= DD, then F = DD.
  • If Labor completion % = 100, then if F < DD, then finish milestone time parameters remain unchanged; if F >= DD, then F = DD – 1.

SCENARIO 4.2: Labor units - units/time by original duration

In this scenario, the planned finish of started activities is determined from current labor completion percentage and start date. The original execution rate is calculated from original duration (BD, "Original duration"), and remaining duration is calculated from that rate. If original duration is missing, scenario 4.1, "Labor units - units/time by actual duration", is applied.

Activity time parameter calculation algorithm:

  • If Labor completion % = 0, then

if S > DD, then S = DD. Then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1;

if S <= DD, then S = DD, then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1.

  • If Labor completion % = 100, then

if S < DD and F > DD, then F = DD - 1, WD = (DD – S)*Cal, AWD = WD, RWD = 0, D = F – S + 1;

if S < DD and F <= DD, then activity time parameters remain unchanged;

if S >= DD, then RWD and AWD remain unchanged, S = (DD – AWD)*Cal, F = (DD + RWD – 1)*Cal, D = F – S + 1, WD = AWD + RWD.

  • If 0 < Labor completion % < 100, then

if DD > S, then F = DD + (BD*((100%-Labor completion %)/100%) – 1)*Cal, AWD = (DD – S)*Cal, RWD = (F – DD + 1)*Cal, WD = AWD + RWD, D = F – S + 1;

if DD <= S, then WD, AWD and RWD remain unchanged, S = (DD – AWD)*Cal, F = (DD + RWD – 1)*Cal, D = F – S + 1.

Start milestone time parameter calculation algorithm:

  • If Labor completion % = 0, then if S > DD, then S = DD; if S <= DD, then S = DD.
  • If Labor completion % = 100, then if S < DD, then start milestone time parameters remain unchanged; if S >= DD, then S = DD – 1.

Finish milestone time parameter calculation algorithm:

  • If Labor completion % = 0, then if F > DD, then F = DD; if F <= DD, then F = DD.
  • If Labor completion % = 100, then if F < DD, then finish milestone time parameters remain unchanged; if F >= DD, then F = DD – 1.

SCENARIO 4.3: Labor units - units/time by baseline duration

In this scenario, the planned finish of started activities is determined from current labor completion percentage and start date. The baseline execution rate is calculated from activity duration in the baseline schedule version (TD), and remaining duration is calculated from that rate. If the activity is missing from the baseline version, the default scenario is applied: scenario 4.1, "Labor units - units/time by actual duration".

Activity time parameter calculation algorithm:

  • If Labor completion % = 0, then

if S > DD, then S = DD. Then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1;

if S <= DD, then S = DD, then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1.

  • If Labor completion % = 100, then

if S < DD and F > DD, then F = DD - 1, WD = (DD – S)*Cal, AWD = WD, RWD = 0, D = F – S + 1;

if S < DD and F <= DD, then activity time parameters remain unchanged;

if S >= DD, then RWD and AWD remain unchanged, S = (DD – AWD)*Cal, F = (DD + RWD – 1)*Cal, D = F – S + 1, WD = AWD + RWD.

  • If 0 < Labor completion % < 100, then

if DD > S, then F = DD + (TD*((100%-Labor completion %)/100%) - 1)*Cal, AWD = (DD – S)*Cal, RWD = (F – DD + 1)*Cal, WD = AWD + RWD, D = F – S + 1;

if DD <= S, then WD, AWD and RWD remain unchanged, S = (DD – AWD)*Cal, F = (DD + RWD – 1)*Cal, D = F – S + 1.

Start milestone time parameter calculation algorithm:

  • If Labor completion % = 0, then if S > DD, then S = DD; if S <= DD, then S = DD.
  • If Labor completion % = 100, then if S < DD, then start milestone time parameters remain unchanged; if S >= DD, then S = DD – 1.

Finish milestone time parameter calculation algorithm:

  • If Labor completion % = 0, then if F > DD, then F = DD; if F <= DD, then F = DD.
  • If Labor completion % = 100, then if F < DD, then finish milestone time parameters remain unchanged; if F >= DD, then F = DD – 1.

SCENARIO 4.4: Labor units - fixed units/time by remaining duration

For activities in progress, this scenario keeps finish unchanged regardless of the labor usage rate, provided the update date is earlier than finish. If the update date is on or after finish, one day is added to finish. Start is calculated from relationships, the update date, and assigned constraints.

Activity time parameter calculation algorithm:

  • If Labor completion % = 0, then

if S > DD, then S = DD. Then AWD = 0, RWD = BD, F = (S + BD – 1)*Cal, D = F – S + 1;

if S <= DD, then S = DD, then AWD = 0, RWD = BD, F = (S + BD – 1)*Cal, D = F – S + 1.

  • If Labor completion % = 100, then

if FFD > DD, then S = FFD, F = LFD, D = F – S + 1, BD = CONST, WD = (F – S + 1)*Cal, AWD = WD, RWD = 0;

if FFD < DD & LFD > DD, then S = FFD, F = LFD, D = F – S + 1, BD = CONST, WD = (F – S + 1)*Cal, AWD = WD, RWD = 0;

if FFD < DD & LFD <= DD, then S = FFD, F = LFD, D = F – S + 1, BD = CONST, WD = (F – S + 1)*Cal, AWD = WD, RWD = 0.

  • If 0 < Labor completion % < 100%, then

if FFD > DD, then S = FFD, F = (S + BD - 1)*Cal, D = F – S + 1, WD = (F – S + 1)*Cal, AWD = 0, RWD = WD;

if FFD < DD & BD – (DD – FFD) > 0, then S = FFD, F = DD + (BD – (DD – FFD))*Cal (provided F >= LFD, if LFD > F, then F = LFD), AWD = DD – FFD, RWD = BD – AWD, WD = RWD + AWD, D = F – S + 1;

if FFD < DD & BD – (DD – FFD) < 0, then S = FFD, F = (DD + 1)* Cal, AWD = DD – FFD, RWD = 1, WD = RWD + AWD, D = F – FFD + 1.

SCENARIO 5.1: Labor units - units/time by actual duration, start/finish by daily actuals

Planned dates are calculated using algorithms similar to scenario 4.1. However, start is set to the first actual labor entry date when labor completion % > 0, and finish is set to the last actual labor entry date when labor completion % = 100. If actual labor is missing, scenario 4.1 is applied. Note: actual values must be approved.

Activity time parameter calculation algorithm:

  • If Labor completion % = 0, then

if S >= DD, then S = DD. Then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1;

if S < DD, then S = DD, then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1.

  • If Labor completion % = 100, then

if S = FFD, where FFD – first actual date, F = LFD, where LFD – last actual date. RWD = 0, AWD = WD, WD = (F – S + 1) * Cal.

  • If 0 < Labor completion % < 100, then

If S < DD, then S = FFD, where FFD – first actual date, F = (DD + (100-%)/(Labor completion %/(DD – S)) – 1)*Cal, AWD = (DD – S)*Cal, RWD = (F – DD + 1)*Cal, WD = RWD, D = F – S + 1;

if S >= DD, then S = FFD, where FFD – first actual date, WD remains unchanged, RWD = WD*(100 - Labor completion %), AWD = WD - RWD

Start milestone time parameter calculation algorithm:

  • If Labor completion % = 0, then if S >= DD, then S = DD; if S < DD, then S = DD.
  • If Labor completion % = 100, then if S < DD, then start milestone time parameters remain unchanged; if S >= DD, then S = DD – 1.

Finish milestone time parameter calculation algorithm:

  • If Labor completion % = 0, then if F >= DD, then F = DD; if F < DD, then F = DD.
  • If Labor completion % = 100, then if F < DD, then finish milestone time parameters remain unchanged; if F >= DD, then F = DD – 1.

SCENARIO 5.2: Labor units - units/time by original duration, start/finish by daily actuals

Planned dates are calculated using algorithms similar to scenario 4.2. However, start is set to the first actual labor entry date when labor completion % > 0, and finish is set to the last actual labor entry date when labor completion % = 100. If actual labor is missing, scenario 4.2 is applied. Note: actual values must be approved.

Activity time parameter calculation algorithm:

  • If Labor completion % = 0, then

S = DD. Then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1;

  • If Labor completion % = 100, then

if S = FFD, where FFD – first actual date, F = LFD, where LFD – last actual date. RWD = 0, AWD = WD, WD = (F – S + 1) * Cal.

  • If 0 < Labor completion % < 100, then

If S < DD, then S = FFD, where FFD – first actual date, F = DD + (BD*((100%-Labor completion %)/100%) – 1)*Cal, AWD = (DD – S)*Cal, RWD = (F – DD + 1)*Cal, WD = RWD + AWD, D = F – S + 1;

if S >= DD, then S = FFD, where FFD – first actual date, WD remains unchanged, RWD = BD*(100 - %), AWD = WD - RWD

Start milestone time parameter calculation algorithm:

  • If Labor completion % = 0, then if S >= DD, then S = DD; if S < DD, then S = DD.
  • If Labor completion % = 100, then if S < DD, then start milestone time parameters remain unchanged; if S >= DD, then S = DD – 1.

Finish milestone time parameter calculation algorithm:

  • If Labor completion % = 0, then if F >= DD, then F = DD; if F < DD, then F = DD.
  • If Labor completion % = 100, then if F < DD, then finish milestone time parameters remain unchanged; if F >= DD, then F = DD – 1.

SCENARIO 5.3: Labor units - units/time by baseline duration, start/finish by daily actuals

Planned dates are calculated using algorithms similar to scenario 4.3. However, start is set to the first actual labor entry date when labor completion % > 0, and finish is set to the last actual labor entry date when labor completion % = 100. If actual labor is missing, scenario 4.3 is applied. Note: actual values must be approved.

Activity time parameter calculation algorithm:

  • If Labor completion % = 0, then

if S >= DD, then S = DD. Then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1;

if S < DD, then S = DD, then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1.

  • If Labor completion % = 100, then

if S = FFD, where FFD – first actual date, F = LFD, where LFD – last actual date. RWD = 0, AWD = WD, WD = (F – S + 1) * Cal.

  • If 0 < Labor completion % < 100, then

If S < DD, then S = FFD, where FFD – first actual date, F = DD + (TD*((100%-Labor completion %)/100%) – 1)*Cal, AWD = (DD – S)*Cal, RWD = (F – DD + 1)*Cal, RWD = WD - AWD, D = F – S + 1;

if S >= DD, then S = FFD, where FFD – first actual date, WD remains unchanged, RWD = TD*(100 - Labor completion %), AWD = WD - RWD

Start milestone time parameter calculation algorithm:

  • If Labor completion % = 0, then if S >= DD, then S = DD; if S < DD, then S = DD.
  • If Labor completion % = 100, then if S < DD, then start milestone time parameters remain unchanged; if S >= DD, then S = DD – 1.

Finish milestone time parameter calculation algorithm:

  • If Labor completion % = 0, then if F >= DD, then F = DD; if F < DD, then F = DD.
  • If Labor completion % = 100, then if F < DD, then finish milestone time parameters remain unchanged; if F >= DD, then F = DD – 1.

SCENARIO 5.4: Labor units - fixed units/time by remaining duration, start/finish by daily actuals

When actual labor has been entered, this scenario sets start to the earliest actual entry date. Finish remains unchanged regardless of actual quantity, provided the update date is earlier than finish. If the update date is on or after finish, one day is added to finish. When Progress = 100, finish is set to the latest actual entry date.

Activity time parameter calculation algorithm:

  • If Labor completion % = 0, then

if S > DD, then S = DD. Then AWD = 0, RWD = BD, F = (S + BD – 1)*Cal, D = F – S + 1;

if S <= DD, then S = DD, then AWD = 0, RWD = BD, F = (S + BD – 1)*Cal, D = F – S + 1.

  • If Labor completion % = 100, then

if FFD > DD, then S = FFD, F = LFD, D = F – S + 1, BD = CONST, WD = (F – S + 1)*Cal, AWD = WD, RWD = 0;

if FFD < DD & LFD > DD, then S = FFD, F = LFD, D = F – S + 1, BD = CONST, WD = (F – S + 1)*Cal, AWD = WD, RWD = 0;

if FFD < DD & LFD <= DD, then S = FFD, F = LFD, D = F – S + 1, BD = CONST, WD = (F – S + 1)*Cal, AWD = WD, RWD = 0.

  • If 0 < Labor completion % < 100%, then

if FFD > DD, then S = FFD, F = (S + BD - 1)*Cal, D = F – S + 1, WD = (F – S + 1)*Cal, AWD = 0, RWD = WD;

if FFD < DD & BD – (DD – FFD) > 0, then S = FFD, F = DD + (BD – (DD – FFD))*Cal (provided F >= LFD, if LFD > F, then F = LFD), AWD = DD – FFD, RWD = BD – AWD, WD = RWD + AWD, D = F – S + 1;

if FFD < DD & BD – (DD – FFD) < 0, then S = FFD, F = (DD + 1)* Cal, AWD = DD – FFD, RWD = 1, WD = RWD + AWD, D = F – FFD + 1.

SCENARIO 6.1: Cost - units/time by actual duration

In this scenario, the planned finish of started activities is determined from current cost completion percentage and start date. The actual cost accrual rate is calculated, and remaining duration is calculated from that rate.

Activity time parameter calculation algorithm:

  • If Cost completion % = 0, then

if S > DD, then S = DD. Then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1;

if S <= DD, then S = DD, then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1.

  • If Cost completion % = 100, then

if S < DD and F > DD, then F = DD - 1, WD = (DD – S)*Cal, AWD = WD, RWD = 0, D = F – S + 1;

if S < DD and F <= DD, then activity time parameters remain unchanged;

if S >= DD, then RWD and AWD remain unchanged, S = (DD – AWD)*Cal, F = (DD + RWD – 1)*Cal, D = F – S + 1, WD = AWD + RWD.

  • If 0 < Cost completion % < 100, then

if DD > S, then F = (DD + (100-%)/(Cost completion % /(DD – S)) – 1)*Cal, AWD = (DD – S)*Cal, RWD = (F – DD + 1)*Cal, WD = AWD + RWD, D =F – S + 1;

if DD <= S, then WD, AWD and RWD remain unchanged, S = (DD – AWD)*Cal, F = (DD + RWD – 1)*Cal, D = F – S + 1.

Start milestone time parameter calculation algorithm:

  • If Cost completion % = 0, then if S > DD, then S = DD; if S <= DD, then S = DD.
  • If Cost completion % = 100, then if S < DD, then start milestone time parameters remain unchanged; if S >= DD, then S = DD – 1.

Finish milestone time parameter calculation algorithm:

  • If Cost completion % = 0, then if F > DD, then F = DD; if F <= DD, then F = DD.
  • If Cost completion % = 100, then if F < DD, then finish milestone time parameters remain unchanged; if F >= DD, then F = DD – 1.

SCENARIO 6.2: Cost - units/time by original duration

In this scenario, the planned finish of started activities is determined from current cost completion percentage and start date. The original execution rate is calculated from original duration (BD, "Original duration"), and remaining duration is calculated from that rate. If original duration is missing, scenario 6.1, "Cost - units/time by actual duration", is applied.

Activity time parameter calculation algorithm:

  • If Cost completion % = 0, then

if S > DD, then S = DD. Then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1;

if S <= DD, then S = DD, then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1.

  • If Cost completion % = 100, then

if S < DD and F > DD, then F = DD - 1, WD = (DD – S)*Cal, AWD = WD, RWD = 0, D = F – S + 1;

if S < DD and F <= DD, then activity time parameters remain unchanged;

if S >= DD, then RWD and AWD remain unchanged, S = (DD – AWD)*Cal, F = (DD + RWD – 1)*Cal, D = F – S + 1, WD = AWD + RWD.

  • If 0 < Cost completion % < 100, then

if DD > S, then F = DD + (BD*((100%-Cost completion %)/100%) – 1)*Cal, AWD = (DD – S)*Cal, RWD = (F – DD + 1)*Cal, WD = AWD + RWD, D = F – S + 1;

if DD <= S, then WD, AWD and RWD remain unchanged, S = (DD – AWD)*Cal, F = (DD + RWD – 1)*Cal, D = F – S + 1.

Start milestone time parameter calculation algorithm:

  • If Cost completion % = 0, then if S > DD, then S = DD; if S <= DD, then S = DD.
  • If Cost completion % = 100, then if S < DD, then start milestone time parameters remain unchanged; if S >= DD, then S = DD – 1.

Finish milestone time parameter calculation algorithm:

  • If Cost completion % = 0, then if F > DD, then F = DD; if F <= DD, then F = DD.
  • If Cost completion % = 100, then if F < DD, then finish milestone time parameters remain unchanged; if F >= DD, then F = DD – 1.

SCENARIO 6.3: Cost - units/time by baseline duration

In this scenario, the planned finish of started activities is determined from current cost completion percentage and start date. The baseline execution rate is calculated from activity duration in the baseline schedule version (TD), and remaining duration is calculated from that rate. If the activity is missing from the baseline version, the default scenario is applied: scenario 6.1, "Cost - units/time by actual duration".

Activity time parameter calculation algorithm:

  • If Cost completion % = 0, then

if S > DD, then S = DD. Then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1;

if S <= DD, then S = DD, then AWD = 0, RWD = WD, F = (S + WD – 1)*Cal, D = F – S + 1.

  • If Cost completion % = 100, then

if S < DD and F > DD, then F = DD - 1, WD = (DD – S)*Cal, AWD = WD, RWD = 0, D = F – S + 1;

if S < DD and F <= DD, then activity time parameters remain unchanged;

if S >= DD, then RWD and AWD remain unchanged, S = (DD – AWD)*Cal, F = (DD + RWD – 1)*Cal, D = F – S + 1, WD = AWD + RWD.

  • If 0 < Cost completion % < 100, then

if DD > S, then F = DD + (TD*((100%-Cost completion %)/100%) - 1)*Cal, AWD = (DD – S)*Cal, RWD = (F – DD + 1)*Cal, WD = AWD + RWD, D = F – S + 1;

if DD <= S, then WD, AWD and RWD remain unchanged, S = (DD – AWD)*Cal, F = (DD + RWD – 1)*Cal, D = F – S + 1.

Start milestone time parameter calculation algorithm:

  • If Cost completion % = 0, then if S > DD, then S = DD; if S <= DD, then S = DD.
  • If Cost completion % = 100, then if S < DD, then start milestone time parameters remain unchanged; if S >= DD, then S = DD – 1.

Finish milestone time parameter calculation algorithm:

  • If Cost completion % = 0, then if F > DD, then F = DD; if F <= DD, then F = DD.
  • If Cost completion % = 100, then if F < DD, then finish milestone time parameters remain unchanged; if F >= DD, then F = DD – 1.

STAGE 2

CALCULATING ACTIVITY/MILESTONE DATES FROM DEPENDENCIES (PREDECESSORS)

Activity and milestone dates calculated from assigned predecessor relationships do not depend on the selected calculation scenario.

  • If % = 0 after stage 1, activity or milestone F or S is determined from assigned predecessor relationships. When there are multiple predecessors, the option giving the latest activity start, start milestone start, or finish milestone finish is selected.
  • If % = 100 after stage 1, F or S remains unchanged regardless of assigned relationships.
  • If 0 < % < 100 after stage 1, S remains unchanged, while F can change only for FF or SF predecessor relationships. F is adjusted to the assigned relationship, and AWD, %, WD, and D are recalculated.