ANNEX 1. SOURCE DATA REQUIREMENTS FOR IMPORT INTO PLAN-R

The PLAN-R construction project management platform allows you to import activity schedules, including network schedules and linear schedules, in various file formats.

The minimum set of required attributes for importing data into PLAN-R, regardless of the imported file format, is:

  • a unique identifier for the activity or work breakdown structure node;
  • the name of the activity or work breakdown structure node.

PLAN-R supports the following file formats for import:

  • .xer files — project data exported from Oracle Primavera, Spider Project, and other systems;
  • .xml files — project data exported from Microsoft Project and other systems;
  • .xlsx files — Microsoft Excel files.

.xlsx files must contain a data table with the following structure:

  • the first row specifies the data type from the list of attribute data types supported in PLAN-R;
  • the second row contains the names of activity or work breakdown structure node attributes;
  • the third and subsequent rows contain attribute values for activities or work breakdown structure nodes.

The following attribute data types are supported in PLAN-R:

Attribute Data Types Supported in PLAN-R

Attribute Type Name
date Date
number Number
string String (text data)
through Cross-version attribute containing text data
boolean Boolean

Attention! When a new Actual version of a schedule is created by importing a file, a cross-version attribute preserves activity values even if those values or the attribute itself are missing from the imported file. Similarly, when a new Actual version is assigned, the attribute preserves values from the Actual version being replaced. This attribute can be used to store codes for linking schedules or linking activities to a BIM model.

System Attributes

Name Field Data Type Properties Attribute Purpose
% of planned labor completedlabour_progress
_on_date
Number [number]Read-only, calculatedPercentage ratio of approved actual labor to approved planned labor as of the current date.

Calculated automatically when you click "Refresh planned cost, PV and labor on date", using the formula:

Labor plan completion % as of date = ∑ Current date - 1 Start Actual ∑ Current date - 1 Start Approved plan

Note: cannot exceed 100%.

Example: if the current date is May 15, 2025, approved actual and planned daily values are totaled through May 14, 2025. Their percentage ratio is then calculated.

PV completion % volume_progress
_on_date
Number [number] Read-only, calculated Percentage ratio of approved actual physical quantity to approved planned physical quantity as of the current date. Calculated automatically when you click "Update planned PV and labor units on date", using the formula:

Physical quantity plan completion % = ∑ Current date - 1 Start Actual ∑ Current date - 1 Start Approved plan * 100

Note: cannot exceed 100%.
Example: if the current date is May 15, 2025, approved actual and planned resource planning values are totaled through May 14, 2025. Their percentage ratio is then calculated.

% by quantity progress_
by_volume
Number [number]Read-only, calculatedPercentage ratio of actual physical quantity to planned physical quantity. Calculated automatically when the attribute values are populated, using the formula:

% by quantity = Actual physical quantity Planned physical quantity * 100

Cannot exceed 100%. When scheduling is calculated using physical quantities, the quantity completion percentage is used as progress.

Note: to ensure that the quantity completion percentage is accurate, approve actual physical quantities from resource planning using "Accepted daily actuals" (see "Managing Actual Data in Daily Planning").

% by costprogress_
by_cost
Number [number]Read-only, calculatedPercentage ratio of actual cost to planned cost. Calculated automatically when the attribute values are populated, using the formula:

% by cost = Actual cost Planned cost * 100

Cannot exceed 100%. When calculating the schedule (see "Annex 2. Schedule Calculation Algorithms for Different Scenarios") using total cost, the cost completion percentage is used as progress.

Note: to ensure that the cost completion percentage is accurate, approve actual costs from resource planning using "Accepted daily actuals" (see "Managing Actual Data in Daily Planning").

% by labor unitsprogress_
by_labour
Number [number]Read-only, calculatedPercentage ratio of actual labor to planned labor. Calculated automatically when the attribute values are populated, using the formula:

% by labor units = Actual labor Planned labor * 100

Cannot exceed 100%. When scheduling is calculated using labor, the labor completion percentage is used as progress.

Note: to ensure that the labor completion percentage is accurate, approve actual labor from resource planning using "Accepted daily actuals" (see "Managing Actual Data in Daily Planning")

In rangein_scopeString [string]ListActivity execution mode used when calculating the schedule (see "Schedule Calculation").
Possible values:
  • "Empty" — the activity or milestone is not moved to either the update date or its late start. Its position remains unchanged if it does not violate relationships or falls after the update date;
  • "Earlier" — the activity or milestone is moved to the update date, taking assigned relationships into account;
  • "Later" — the activity or milestone start is moved beyond the update date by its free float;
  • "Stretch" — the activity start and finish are determined by relationships and free float. Duration is variable in this mode and can increase or decrease, down to the original duration.
Visual profilebim_appearance
_profile
String [string]EditableVisual profile value. The visual profile controls the display of the BIM model element linked to the activity (see "BIM-R. Working with Information Models") during 4D playback (see "4D Player").

The attribute contains predefined visual profiles: Install, Maintain, Neutral (invisible), Remove, and Temporary. You can configure a custom visual profile and assign it to an activity.

Visual profiles determine the element color before, during, and after work on the element. They can also simulate the direction in which an element appears in the 3D model, such as bottom up or top to bottom.

Constraint Impact on Late Dateslate_date_
constraint_impact
String [string]Read-only, calculatedCalculated automatically during scheduling when "Perform an additional calculation of late dates without constraints / deadline" is selected.
The attribute has four possible values:
  • "Empty" — for rows whose late dates are not calculated, including activities with "Completed" status;
  • "No impact" — late dates are calculated from assigned relationships, working backward, without the influence of constraints or deadlines;
  • "Self constraint / deadline" — the current activity has constraints or a deadline affecting its late dates. Removing these constraints would change its late dates.

"Successor constraint / deadline" — one or more successors have constraints or deadlines that affect the current activity's late dates.

Date of changeupdated_atDate [date]Read-only, automatically populatedActivity modification date. Populated automatically by PLAN-R when:
  • importing a project or schedule, or performing a batch import;
  • calculating the schedule;
  • manually changing activity information in the schedule;
  • globally replacing schedule attributes;
  • performing schedule or project calculations;
  • assigning relationships between schedule activities;
  • updating baseline dates;
  • updating calculated attributes;
  • populating values using checkboxes.
Start limit datestart_limit_dateDate [date]EditableActivity start constraint date. Used together with "Start limit type".
Finish limit datefinish_limit_dateDate [date]EditableActivity finish constraint date. Used together with "Finishing limit type".
Creation datecreated_atDate [date]Read-only, automatically populatedActivity creation date. Populated automatically by PLAN-R when:
  • creating an activity in the PLAN-R interface;
  • copying an activity, schedule version, or project;
  • importing a schedule version.
DeadlinedeadlineDate [date]EditableLatest permitted activity completion date. Entered manually by the user.
Unit of measuremeasureString [string]EditableThe unit in which the physical quantity or resource quantity is expressed.

A value entered in "Unit of measure" is used in resource planning (see "Planning in PLAN-R") and included in parentheses in the "Name" attribute.

Units/timebase-intensity
-by-volume
Number [number]EditablePhysical or resource quantity that can be completed in one working hour. Defines the activity production rate for physical quantities or resources.

Used when calculating the schedule with scenarios "2.1 By physical quantity production rate" and "3.1 By physical quantity production rate, start/finish from daily actuals".

SourceoriginString [string]Read-onlyIdentifies the origin of a record. Distinguishes activities created in PLAN-R from those imported from external systems, such as MS Project.
Original durationinitial-durationNumber [number]Editable, calculatedOriginal working duration in days.

Automatically set equal to working duration when the activity has not started ("Progress" = 0 or "Status" = "Not started");

Once activity progress is recorded, the value is fixed and no longer follows working duration. You can adjust it if necessary. Used in the following schedule calculation scenarios:

  • "2.3 PHYSICAL QUANTITY PRODUCTION RATE BASED ON ORIGINAL DURATION";
  • "3.3 PHYSICAL QUANTITY PRODUCTION RATE BASED ON ORIGINAL DURATION, START/FINISH FROM DAILY ACTUALS";
  • "4.2 LABOR PRODUCTION RATE BASED ON ORIGINAL DURATION";
  • "6.2 COST ACCRUAL RATE BASED ON ORIGINAL DURATION".
Initial IDorigin_idString [string]EditableOriginal ID of a record imported from an external system.
Calendar durationdurationNumber [number]Read-only, calculatedActivity duration in calendar days, including weekends and holidays in its assigned calendar. Calculated in PLAN-R from "Start"/"Finish" or "Start"/"Work duration"/"Calendar". Calculated automatically and cannot be entered manually.

Example: an activity has a working duration of five days and a five-day working calendar. Its calendar duration is seven days: five working days plus two nonworking days.

CalendarcalendarString [string]ListName of the calendar defining working and nonworking time. Each activity can be assigned a calendar that accounts for weekends, holidays, working arrangements, and other requirements appropriate to its assignee. New activities use "PLAN-R: 7 days" by default. For more information, see "Creating and Assigning Calendars".

Working, original, calendar, and remaining working durations are calculated using the assigned activity calendar.

Note: when importing schedules into PLAN-R, check each activity's assigned calendar. Otherwise, activity dates may differ from the source.

Primary resource codevolume_codeString [string]EditablePhysical quantity / Controlling Resource identifier. Used in COST-R to link a work type to a local cost estimate calculation.
Assignee’s commentexecutor
_comment
String [string]EditableStores the assignee's activity comments.
ResponsibleexecutorString [string]EditableContains activity assignee information. Used to restrict which activities in a schedule version are visible to a user.

To restrict activity visibility:

  1. Set the "Assignee" attribute on the "Users" tab in "Administration" (see "Assigning an Activity Assignee");
  2. Set the "Assignee" attribute for the corresponding schedule version activities. Example: a project has several contractors, and access to another contractor's activities or schedule information must be restricted. Set "Contractor No. 1" for the contractor's users in "Administration", then set the same attribute value on Contractor No. 1's activities.
SupervisorcuratorString [string]ListName of a user authorized to approve actual values in resource planning. Multiple curators can be assigned to an activity.

Note: only employees with access to the schedule can be assigned as curators.

NamenameString [string]EditableDescription or designation of an activity in the schedule. Identifies the activity and normally contains a brief, clear description of the task or stage to complete.

Required when importing files, including the "Update" and "Delete" import scenarios.

WBS node nameparent_nameString [string]Read-onlyName of the parent WBS node containing the schedule activity.
Primary resource namevolumeString [string]EditableDescription of the measurable physical quantity / Controlling Resource to be achieved when performing the schedule activity.
Organisation unitorg_unitString [string]EditableStores additional information about the activity's place in the enterprise organizational structure.
Remaining work durationremaining-work
-duration
Number [number]Editable, calculatedWorking time needed to finish the activity from the current moment.

Calculated:

  1. during scheduling; the value depends on the selected calculation scenario;
  2. when "Start", "Finish", "Progress", "Work duration", or "Actual duration" changes.
    You can manually enter remaining working duration if necessary.
PV variance at datevalume_lag
_on_date
Number [number]Read-only, calculatedIndicates variances between approved planned and actual daily physical quantities up to, but excluding, the current date. Calculated as total daily actual physical quantities minus total daily approved planned physical quantities:

Physical quantity variance as of date = ∑ Current date Daily actual physical quantity -
∑ Current date Daily approved planned physical quantity

Updated when you click "Refresh planned cost, PV and labor on date".

Work duration variance from the BLtarget-lag-by
-work-duration
Number [number]Read-only, calculatedIndicates working duration variances between the Actual and baseline schedule versions. Calculated as Actual version working duration minus baseline version working duration.

Work duration variance from the BL =
Working duration Baseline version - Working duration Actual version

Values are displayed only when a baseline schedule version and a corresponding baseline activity exist. Activities are matched by "ID". After creating or assigning a new baseline version, or changing values in the current baseline version, update this attribute in the Actual version.

Start variance from BLtarget-lag
-by-start
Number [number]Read-only, calculatedIndicates start variances for an activity or start milestone between the Actual and baseline versions. Calculated as the difference between their start dates.

Start variance from BL =
Start Baseline version - Start Actual version

Values are displayed only when a baseline schedule version and a corresponding baseline activity exist. Activities are matched by "ID". After creating or assigning a new baseline version, or changing values in the current baseline version, update this attribute in the Actual version.

Cost variance as of datecost_lag
_on_date
Number [number]Read-only, calculatedIndicates variances between approved planned and actual daily costs up to, but excluding, the current date. Calculated as total daily actual costs minus total daily approved planned costs in the Actual version.

Cost variance as of date = ∑ Current date Daily actual cost -
∑ Current date Daily planned cost

Updated when you click "Refresh planned cost, PV and labor on date".

Labor variance to datelabour_lag
_on_date
Number [number]Read-only, calculatedIndicates variances between approved planned and actual daily labor up to, but excluding, the current date. Calculated as total daily actual labor minus total daily approved planned labor:

Labor variance as of date = ∑ Current date Daily actual labor -
∑ Current date Daily approved planned labor

Usage: updated when you click "Refresh planned cost, PV and labor on date".

Finish variance from BLtarget-lag
-by-finish
Number [number]Read-only, calculatedIndicates finish variances for an activity or finish milestone between the Actual and baseline versions. Calculated as the difference between their finish dates.

Finish variance from BL =
Finish Baseline version - Finish Actual version

Values are displayed only when a baseline schedule version and a corresponding linked activity in that version exist. Activities are matched by "ID". After creating or assigning a new baseline version, or changing the current baseline version, update this attribute in the Actual version.

Estimated completion %estimate_
progress
Number [number]EditableActivity completion percentage estimated by the assignee. Can be used to adjust activity progress. Values can be entered:
  • when editing a schedule version (see "Editing a Schedule Version");
  • through the data update form in the personal account (see "User Personal Account").

To update data through the personal account form, enable schedule update notifications (see "Viewing User Notifications in the Personal Account") and assign an assignee to the schedule activity (see "Assigning an Activity Assignee").

The estimated completion percentage can be considered during schedule calculation (see "Schedule Calculation"). To include estimated data in schedule calculations, first approve the data entered for activities. Estimated data can be approved by a user with the appropriate permissions (see "Adding User Roles") or by a curator assigned to the schedule activity.

Estimated data awaiting approval is displayed with a gray background on schedule activities. To quickly find activities with unapproved estimated data, use the approval filter (see "Filtering").

Estimated startestimate_startDate [date]EditableApproximate activity start estimated by the assignee. Can be used to adjust the activity start and, in some cases, take precedence over the original start. Values can be entered:

To update data through the personal account form, enable schedule update notifications (see "Viewing User Notifications in the Personal Account") and assign an assignee to the schedule activity (see "Assigning an Activity Assignee").

The estimated start can be considered during schedule calculation (see "Schedule Calculation"). To include estimated data in schedule calculations, first approve the data entered for activities. Estimated data can be approved by a user with the appropriate permissions (see "Adding User Roles") or by a curator assigned to the schedule activity.

Estimated data awaiting approval is displayed with a gray background on schedule activities. To quickly find activities with unapproved estimated data, use the approval filter (see "Filtering").

Estimated finishestimate_finishDate [date]EditableApproximate activity finish estimated by the assignee. Can be used to adjust the activity finish and, in some cases, take precedence over the original finish.
Values can be entered:

To update data through the personal account form, enable schedule update notifications (see "Viewing User Notifications in the Personal Account") and assign an assignee (see "Assigning an Activity Assignee") to the schedule activity.

The estimated finish can be considered during schedule calculation (see "Schedule Calculation"). To include estimated data in schedule calculations, first approve the data entered for activities. Estimated data can be approved by a user with the appropriate permissions (see "Adding User Roles") or by a curator assigned to the schedule activity.

Estimated data awaiting approval is displayed with a gray background on schedule activities. To quickly find activities with unapproved estimated data, use the approval filter (see "Filtering").

Planvolume-planNumber [number]EditablePlanned work expressed as physical or resource quantity. Commonly used in construction and production schedules to track activity progress by comparing completed quantities or resources with planned quantities.

Values can be automatically distributed by day in daily planning (see "Daily Distribution of Plan and Actual Data in Simplified Planning") and (see "Daily Plan Distribution in Resource Planning").

Plan PV for datevalume_plan
_on_date
Number [number]Read-only, calculatedTotal distributed planned physical quantity for the activity in resource planning up to, but excluding, the current date. Calculated from approved planned values:

Plan PV for date = ∑ Current date Approved plan Physical quantity

Usage: compares planned physical quantity with its distributed value. Shows how much physical work should have been completed by the current date.

Updated when you click "Refresh planned cost, PV and labor on date".

Planned costcost-planNumber [number]EditablePlanned activity cost. May include materials, labor resources, equipment, and other items required to complete the activity.

Values can be automatically distributed by day in daily planning (see "Daily Distribution of Plan and Actual Data in Simplified Planning") and (see "Daily Plan Distribution in Resource Planning").

Planned cost on datecost_plan
_on_date
Number [number]Read-only, calculatedTotal distributed planned activity cost in resource planning up to, but excluding, the current date. Calculated from the approved plan in the Actual version.

Planned cost as of date = ∑ Current date Approved plan Cost
Cost plan on date by BLtarget_cost_
plan_on_datee
Number [number]Read-only, calculatedTotal distributed planned activity cost in resource planning up to, but excluding, the current date. Calculated from approved baseline planned values only for records of type "Activity" in both the Actual and baseline versions, with daily plan/actual versioning enabled.

Baseline planned cost as of date =
∑ Current date Approved baseline plan Cost

Updated when you click "Refresh planned cost, PV and labor on date". Not calculated when daily plan/actual versioning is disabled.

Plan cost by operating PR distributionplan_price
_by_operative
Number [number]Read-only, calculatedTotal planned activity expenditure expressed per unit of planned physical quantity / Controlling Resource:

Planned cost from operational CR (physical quantity) distribution =
∑ (Operational CR (physical quantity) plan * Rate)

The operational CR (physical quantity) plan is taken from each individual activity execution day in resource planning.

Note: updated when you click "Accept actuals".

Planned cost (distributed rate and operational PR distribution)plan_price_by_
allocation_
and_operative
Number [number]Read-only, calculatedTotal planned expenditure for each individual activity execution day expressed per unit of planned physical quantity / Controlling Resource:

Planned cost from distributed rate
and operational CR (physical quantity) distribution =
∑ (Operational CR (physical quantity) plan * Distributed rate)

The distributed rate and operational CR (physical quantity) plan are taken from each individual activity execution day in resource planning.

Note: updated when you click "Accept actuals".

Planned cost (distributed rate and accepted PR distribution)plan_price
_by_accepted
Number [number]Read-only, calculatedTotal planned expenditure for each individual activity execution day expressed per unit of planned physical quantity / Controlling Resource:

Planned cost from distributed rate
and approved CR (physical quantity) distribution =
∑ (Approved CR (physical quantity) plan * Distributed rate)

The distributed rate and approved CR (physical quantity) plan are taken from each individual activity execution day in resource planning.

Note: updated when you click "Accept actuals".

Cost plan by primary resourcecost_plan_
main_resource
Number [number]Read-only, calculatedPlanned Controlling Resource cost. Calculated automatically using the formula:

Planned cost from CR resources = Approved plan * Rate
Plan cost by accepted PR distributionplan_price
_by_allocation
Number [number]Read-only, calculatedTotal planned activity expenditure expressed per unit of planned physical quantity / Controlling Resource:

Planned cost from approved CR (physical quantity) distribution =
∑ (Approved CR (physical quantity) plan * Rate)

The approved CR (physical quantity) plan is taken from each individual activity execution day in resource planning.

Note: updated when you click "Accept actuals".

PV plan on date by BLtarget_volume
_plan_on_date
Number [number]Read-only, calculatedTotal distributed planned physical quantity in resource planning up to, but excluding, the current date. Calculated from approved baseline planned values only for records of type "Activity" in both the Actual and baseline versions, with daily plan/actual versioning enabled.

Baseline planned physical quantity as of date =
∑ Current date Approved baseline plan Physical quantity

Updated when you click "Refresh planned cost, PV and labor on date". Not calculated when daily plan/actual versioning is disabled.

Planned labor unitslabour-planNumber [number]EditablePlanned work expressed as labor. Labor is expressed in person-days. Values can be automatically distributed by day in daily planning (see "Daily Distribution of Plan and Actual Data in Simplified Planning") and (see "Daily Plan Distribution in Resource Planning").
Planned labor units on datelabour_plan
_on_date
Number [number]Read-only, calculatedTotal distributed planned activity labor in resource planning (see "Managing Actual Data in Daily Planning"). up to, but excluding, the current date. Calculated from approved planned values:

Planned labor as of date = ∑ Current date Approved plan Labor

Usage: compares planned labor with its distributed value. Shows how much labor should have been used on the activity by the current date.

Updated when you click "Refresh planned cost, PV and labor on date".

Planned labor to date (BL)target_labour
_plan_on_date
Number [number]Read-only, calculatedTotal distributed planned activity labor in resource planning up to, but excluding, the current date. Calculated from approved baseline planned values only for records of type "Activity" in both the Actual and baseline versions, with daily plan/actual versioning enabled.

Planned labor to date (BL) =
∑ Current date Approved baseline plan Labor

Updated when you click "Refresh planned cost, PV and labor on date". Not calculated when daily plan/actual versioning is disabled.

Planned labor units by primary resourcelabour_plan
_main_resource
Number [number]Read-only, calculatedPlanned Controlling Resource labor. Calculated automatically using the formula:

Planned labor from CR resources = CR plan * Unit labor requirements
Late startlate_startDate [date]Read-only, calculatedLatest possible activity start without delaying the overall schedule finish. Calculated automatically during scheduling (see "Annex 2. Schedule Calculation Algorithms for Different Scenarios") from the critical path, constraints, and activity dependencies.
Late start (no constraint / deadline)late_start
_no_constraint
Date [date]Read-only, calculatedCalculated automatically during scheduling when "Perform an additional calculation of late dates without constraints / deadline" is selected.

Late start calculated backward through the network model without activity constraints or deadlines.

Late finishlate_finishDate [date]Read-only, calculatedLatest possible activity finish without delaying the overall schedule finish. Calculated automatically during scheduling (see "Annex 2. Schedule Calculation Algorithms for Different Scenarios") from the critical path, constraints, and activity dependencies.
Late finish (no constraint / deadline)late_finish
_no_constraint
Date [date]Read-only, calculatedCalculated automatically during scheduling when "Perform an additional calculation of late dates without constraints / deadline" is selected.

Late finish calculated backward through the network model without activity constraints or deadlines.

Total floatfull_reserveNumber [number]Read-only, calculatedTime in working days or hours by which an activity can be delayed without delaying the overall schedule finish.

Total float can be positive or negative. Negative float may indicate activity constraints or a violation of the technological execution sequence.

By default, activities with total float of zero or less are considered critical. You can specify another total float threshold for identifying critical activities by changing "Critical path float" on the "General" tab in the schedule settings. Calculated automatically during scheduling (see "Annex 2. Schedule Calculation Algorithms for Different Scenarios") of the schedule.

Total float (no constraint / deadline)total_float
_no_constraint
Number [number]Read-only, calculatedCalculated automatically during scheduling when "Perform an additional calculation of late dates without constraints / deadline" is selected.

Difference between activity late dates calculated without constraints and its early dates. Shows how much the activity can be extended or delayed without affecting the schedule finish.

Unlike "Total float", this attribute excludes the influence of constraints and deadlines on late dates, allowing the activity's actual effect on the schedule dates to be assessed.

Successorsrelation-outString [string]Read-only, calculatedID of the successor activity related to the start or finish of this activity. Determined by assigned schedule activity relationships (see "Configuring Relationships Between Schedule Activities"); multiple successor IDs are separated by commas.
Predecessorsrelation-inString [string]Read-only, calculatedID of the predecessor activity governing the start or finish of this activity. Determined by assigned schedule activity relationships (see "Configuring Relationships Between Schedule Activities"); multiple predecessor IDs are separated by commas.
ProgressprogressNumber [number]Editable, calculatedActivity completion percentage. Cannot exceed 100%.

Calculated:

  1. during scheduling; the value depends on the selected calculation scenario;
  2. when "Finish", "Status", "Work duration", "Remaining work duration", or "Actual duration" changes.

You can adjust the attribute value if necessary.

WBS pathparents_
name_path
String [string]Read-onlyFull hierarchical path from the topmost WBS node to the selected schedule activity, including all intermediate parent levels.

For example, an activity named "Foundation" belongs to the "Underground Work" WBS node under "River Hotel". Its "WBS path" is "River Hotel/Underground Work/Foundation".

Work durationwork-durationNumber [number]Editable, calculatedActivity execution duration in working hours or days.

Calculated:

  1. during scheduling; the value depends on the selected calculation scenario;
  2. when "Finish", "Remaining work duration", or "Actual duration" changes.

By default, a newly created activity has a working duration of five working days or 40 hours under the standard PLAN-R calendar.

BL durationtarget-work-durationNumber [number]Read-only, calculatedWorking duration from the baseline schedule version. Used to analyze duration variances in the Actual version.

Values are displayed only when a baseline schedule version and a corresponding linked activity in that version exist. Activities are matched by "ID". After creating or assigning a new baseline version, or changing the current baseline version, update this attribute in the Actual version.

Early startearly_startDate [date]Read-only, calculatedEquals "Start" by default. An exception occurs during schedule calculation (see "Annex 2. Schedule Calculation Algorithms for Different Scenarios")when the scheduling range attribute is set to "Later". Before applying late dates to "Start", PLAN-R records "Early start", preserving the original start value.
Early finishearly_finishDate [date]Read-only, calculatedEquals "Finish" by default. An exception occurs during schedule calculation (see "Annex 2. Schedule Calculation Algorithms for Different Scenarios")when the scheduling range attribute is set to "Later". Before applying late dates to "Finish", PLAN-R records "Early finish", preserving the original finish value.
Calculated finishcalculated_finishDate [date]Read-only, calculatedForecast activity completion date calculated using physical quantity production rate based on actual progress (SCENARIO 3.2: PHYSICAL QUANTITY PRODUCTION RATE BASED ON ACTUAL DURATION, START/FINISH FROM DAILY ACTUALS), actual activity dates, duration, and working calendar. Unlike the planned date, it provides a realistic forecast for identifying delays or advances and making operational decisions. Updated when you click "Update calculated finish".
Free floatfree_reserveNumber [number]Read-only, calculatedMaximum time in working days or hours by which an activity can be delayed without delaying any successor's start.

Calculated automatically during schedule calculation.

Free float calculation by relationship type is described in "Schedule Calculation", Table 5. Free Float Calculation by Relationship Type.

Estimate-Based Costcostr_cost_planNumber [number]Read-onlyAttribute used in COST-R. Calculated when creating a schedule version from the PDC.

The "Estimate-Based Cost" system attribute receives the value of "Cost with additionaly coefficients".

Estimate-Based Quantitycostr_volume_planNumber [number]Read-onlyAttribute used in COST-R. Calculated when creating a schedule version from the PDC.

The "Estimate-Based Quantity" attribute receives the value of "Quantity".

Estimate-Based Labor unitscostr_labour_planNumber [number]Read-onlyAttribute used in COST-R. Calculated when creating a schedule version from the PDC.

The "Estimate-Based Labor units" attribute receives the greater of "Labor" and "Machine hours".

Createdcreated_byString [string]Read-onlyName and login of the user who created the activity. Populated automatically when the activity is created.
RatepriceNumber [number]EditableCost of using a physical quantity or resource per unit of time or per unit of physical quantity or resource.

The entered value is displayed in the "Rate" column in resource planning.

Used to calculate planned cost from operational CR (physical quantity) distribution, planned cost from approved CR (physical quantity) distribution, and actual cost from actual CR (physical quantity) distribution.

StartstartDate [date]Editable, calculatedPlanned or actual activity start in the schedule version.

When "Status" = "Not started", displays planned start. When "Status" ≠ "Not started", displays actual start, and the start date is fixed.

May change during scheduling, depending on the calculation scenario. You can adjust the value if necessary.

StatusstatusString [string]ListCurrent activity execution status. Possible values:
  • "Not started" — activity execution has not begun;
  • "In progress" — activity execution has begun. "Start" contains the actual start and is not shifted during schedule calculation (see "Schedule Calculation");
  • "Completed" — activity execution is complete.

Status is set automatically when activity progress is entered. You can set it manually if necessary.

Aggregation attributesumme_codeString [string]ListDefines the activity grouping rule. PLAN-R collects all schedule activities, including activities from other project schedules, whose specified attribute value matches the summary activity's value, and groups them under it (see "Summary Activities").

The aggregation attribute can have the following types:

  • a custom attribute of type "String";
  • an attribute of type "List";
  • a system attribute with the "String" data type.
Typewbs-typeString [string]ListGraphical representation of the record type in the schedule version.
  • activity with no progress;
  • activity with progress;
  • completed activity;
  • start milestone;
  • finish milestone;
  • draft;
  • summary activity.
Start limit typestart_limit_typeString [string]ListAssigned activity start constraint. Possible values:
  • "Empty" — no constraint is assigned;
  • "No earlier than" — the activity must not start before "Start limit date". Assigned relationships are respected;
  • "No later than" — the activity must start no later than "Start limit date". Assigned relationships are respected;
  • "On date" — the activity must start on "Start limit date". This constraint may violate assigned relationships. If the update date is later than the constraint date and the activity is "Not started", the constraint is ignored and the start is shifted.
Finishing limit typefinish_limit_typeString [string]ListAssigned activity finish constraint. Possible values:
  • "Empty" — no constraint is assigned;
  • "No earlier than" — the activity must not finish before "Finish limit date". Assigned relationships are respected;
  • "No later than" — the activity must finish no later than "Finish limit date". Assigned relationships are respected;
  • "On date" — the activity must finish on "Finish limit date". This constraint may violate assigned relationships. If the update date is later than the constraint date and the activity is not "Completed", the constraint is ignored and the finish is shifted.
Scenario typetimetable-scriptString [string]ListIndicates an individual schedule calculation scenario (see "Annex 2. Schedule Calculation Algorithms for Different Scenarios")assigned to the activity in the schedule version. The activity's scenario takes precedence over the general scenario selected in the schedule calculation menu.

Example: a schedule version uses "UNIFORM BY COMPLETION %", while its milestones use "Fixed dates" to fix stage dates.

Labor constantspecific_labour_costsNumber [number]EditableLabor hours per unit of physical quantity or resource. Can be entered on the "Activity card" and "Resource planning" tabs.

In COST-R, when creating a schedule version from the PDC using estimate data, calculated using the formula:

Labor constant = Labor Quantity

Also used to calculate production rate.

Refined floatrefined_reserveNumber [number]Read-only, calculatedPermitted activity delay that does not delay the overall schedule finish. Refined float accounts for:

• Activity relationships;
• Activity and resource calendars;
• "In progress" and "Completed" activity statuses;
• Activities scheduled outside network logic: fixed-date constraints, scenarios "1.4 Fixed dates" and "1.6 Fixed dates and execution", and estimated data priority.

Calculated automatically during schedule calculation and when activity parameters affecting completion dates are manually adjusted.

Include in nodes and analyticscalculation_inclusionBoolean [boolean]EditableWhen selected, PLAN-R totals activity cost and labor attributes at WBS nodes and in Enterprise Project Structure analytics.
Actualvolume-factNumber [number]EditableCompleted work expressed as physical quantity or resource quantity.

Values can be automatically distributed by day in daily planning (see "Daily Distribution of Plan and Actual Data in Simplified Planning") and (see "Daily Plan Distribution in Resource Planning"). The plan can also be redistributed using entered actual values.

Values entered directly into "Actual" in the WBS table do not require approval. Actual values collected through resource planning require approval. Approval transfers the total daily actual values for the activity to the WBS table.

Actual durationduration-factNumber [number]Editable, calculatedTime actually spent executing the activity from its start through completion or the schedule update time.
Actual costcost-factNumber [number]EditableCompleted work expressed as cost.

Values can be automatically distributed by day in daily planning (see "Daily Distribution of Plan and Actual Data in Simplified Planning") and (see "Daily Plan Distribution in Resource Planning"). The plan can also be redistributed using entered actual values.

Values entered directly into "Actual cost" in the WBS table do not require approval. Actual values collected through resource planning require approval. Approval transfers the total daily actual values for the activity to the WBS table.

Actual cost (distributed rate and actual PR distribution)fact_cost_
by_fact_price
Number [number]Read-only, calculatedTotal actual expenditure for each individual activity execution day expressed per unit of actual physical quantity / Controlling Resource:

Actual cost from distributed rate
and actual CR (physical quantity) distribution =
∑ (Actual CR (physical quantity) * Distributed rate)

The distributed rate and actual CR (physical quantity) values are taken from each individual activity execution day in resource planning.

Note: updated when you click "Accept actuals".

Actual cost by primary resourcecost_fact
_main_resource
Number [number]Read-only, calculatedSum of products based on approved Controlling Resource actual quantities:

Actual cost from CR resources =
∑ Approved CR actual * Rate
Actual cost by actual PR distributionfact_price
_by_allocation
Number [number]Read-only, calculatedTotal actual activity expenditure expressed per unit of actual physical quantity / Controlling Resource:

Actual cost from actual CR (physical quantity) distribution =
∑ (Actual CR (physical quantity) * Rate)

Actual CR (physical quantity) values are taken from each individual activity execution day in resource planning.

Note: updated when you click "Accept actuals".

Actual labor unitslabour-factNumber [number]EditableCompleted work expressed as labor.

Values can be automatically distributed by day in daily planning (see "Daily Distribution of Plan and Actual Data in Simplified Planning") and (see "Daily Plan Distribution in Resource Planning"). The plan can also be redistributed using entered actual values.

Values entered directly into "Actual labor units" in the WBS table do not require approval. Actual values collected through resource planning require approval. Approval transfers the total daily actual values for the activity to the WBS table.

Actual labor units by primary resourcelabour_fact
_main_resource
Number [number]Read-only, calculatedSum of approved Controlling Resource actual quantities multiplied by unit labor requirements:

Actual labor from CR resources =
∑ Approved CR actual * Unit labor requirements

Actual CR (physical quantity) values are taken from each individual activity execution day in resource planning.

FinishfinishDate [date]Editable, calculatedPlanned or actual activity finish. Can be entered manually or calculated automatically in PLAN-R when progress is not 100 and status is "Not started" or "In progress"; otherwise, finish remains unchanged. Entering a date manually changes working duration and progress. Contains the planned or actual activity finish in the schedule version.

When "Status" ≠ "Completed", displays planned finish. When "Status" = "Completed", displays actual finish.

Calculated:

  1. during scheduling; the value depends on the selected calculation scenario;
  2. when "Start", "Work duration", "Remaining work duration", or "Actual duration" changes.

You can adjust the attribute value if necessary.

Baseline starttarget-startDate [date]Read-onlyActivity start from the baseline schedule version.

Used to analyze activity start variances in the Actual schedule version.

Values are displayed only when a baseline schedule version and a corresponding linked activity in that version exist. Activities are matched by "ID". After creating or assigning a new baseline version, or changing the current baseline version, update this attribute in the Actual version.

Baseline finishtarget-finishDate [date]Read-onlyActivity finish from the baseline schedule version.

Used to analyze activity finish variances in the Actual schedule version.

Values are displayed only when a baseline schedule version and a corresponding linked activity in that version exist. Activities are matched by "ID". After creating or assigning a new baseline version, or changing the current baseline version, update this attribute in the Actual version.

IDcodeString [string]EditableUnique activity identifier. Assigned automatically to each activity added through the schedule interface, with a maximum of 20 characters.

You can enter an ID for a selected record or configure prefix/postfix masks and an increment in "Node settings", separately for activity and node IDs. Configure activity and node ID generation rules on the "General" tab in schedule settings (see "Editing Attribute Values and Work Packages").

WBS node IDmaterial-pathString [string]Read-onlyID of the parent node containing the activity.

Identifies the parent WBS node when importing an .xlsx file using "Update version data". Determines the record's position in the WBS, whether it is an activity, WBS node, start milestone, or finish milestone. Can be used when:

  • adding a new record: enter the parent node ID in the "WBS node ID" material-path column in the schedule template;
  • changing a record's position: change its WBS node ID in the schedule template.

Populated automatically when a new schedule version is created by import.

An attribute with the wbs-level data type contains an integer identifying a WBS node and defining its level.

An attribute with the predecessors data type contains a list of predecessor activities linked by technological dependencies. The list uses the following format:

code_1:relation_type+lag;code_2:relation_type+lag;…

where:

  • code_1, code_2 — unique predecessor activity IDs (values of the attribute with the code data type);
  • relation_type — activity relationship type. Possible values: FS, SS, FF, SF (finish-to-start, start-to-start, finish-to-finish, start-to-finish). If omitted, FS is used by default;
  • lag — relationship lag expressed as a positive or negative integer. Defaults to 0 and need not be explicitly specified;
  • ; — separator between predecessor activities.

Example predecessor list:

A1100; A1200:SS; A1300:FF5; A1400:FF-10

Example .xlsx Import Template:

register imageExample .xlsx File for Export to PLAN-R