ENTERPRISE PROJECT STRUCTURE ANALYTICS
In PLAN-R, the "Analytics" tab in the Enterprise Project Structure provides analytics for Space, Project Group, Project, and Schedule nodes.
Analytics are not available for Schedule Group nodes.
Enterprise Project Structure Indicators
PLAN-R uses various indicators to show schedule delays and cost overruns for projects, project groups, and schedules, as well as missing relevant data. The indicators are described in the table below.
Table: Enterprise Project Structure Indicator Definitions
| Indicator Name | Indicator | Meaning | Inheritance | ||
|---|---|---|---|---|---|
| Forecast finish delay indicator (1) | ![]() |
Displayed for a Schedule node when forecast duration exceeds planned duration. Not displayed if the update date of the Actual schedule version is later than the finish date of its latest activity. | A Project node inherits the indicator when at least one of its child nodes has the corresponding indicator. | ||
| Forecast cost overrun indicator (2) | ![]() |
Displayed for a Schedule node when forecast cost from the Actual version exceeds planned cost from the Baseline version. Not displayed if the update date of the Actual version is later than the finish date of its latest activity. | |||
| Missing Actual schedule version indicator (3) | ![]() |
Displayed for a Schedule node that has no Actual version. Disappears when a new version is created and assigned the Actual status. | |||
| Schedule not updated for more than 30 days indicator (4) | ![]() |
Displayed when more than 30 calendar days have elapsed since the Actual schedule version was last updated. Disappears when a new Actual version is imported. | |||
| Schedule quality indicator (5) | ![]() |
Displayed for a Schedule node when its quality is below 30%. | |||
| Indicators of issues in child elements (6) | ![]() |
Displayed on Space or Project Group nodes only when at least one child node has a schedule or cost variance, or lacks current data. These light-gray indicators provide a summary signal of issues within the Enterprise Project Structure. | |||
For details about planned and forecast duration, see Schedule Analytics for Projects, Schedules, and Versions. For forecast and planned cost, see Cost Analytics for Projects, Project Groups, and Schedules. For schedule quality, see Work Quality Analytics for Projects and Schedules.
Enterprise Project Structure Indicators
Schedule Analytics for Projects, Schedules, and Versions
Schedule analytics require no special configuration and are available when the project contains an Actual schedule version.
Schedule analytics (1) become available when you select the corresponding project, schedule, or version in the Enterprise Project Structure (2).
Table: Schedule Analytics Metrics by EPS Node Type
| Metric | EPS Node Type | ||
|---|---|---|---|
| Schedule / Version | Project | ||
| "Planned duration" (3) | Period from the earliest activity start to the latest activity finish in the Baseline version (4), without applying the working calendar: calendar duration in days. | Period from the earliest activity start across the project's Baseline schedule versions (4) to the latest activity finish across those versions, without applying working calendars: project calendar duration in days. | |
| "Forecast duration" (5) | Period from the earliest activity start to the latest activity finish in the Actual version (6), without applying the working calendar: calendar duration in days. | Period from the earliest activity start across the project's Actual schedule versions (6) to the latest activity finish across those versions, without applying working calendars: project calendar duration in days. | |
| "Time elapsed since actual start" (7) | Period from the earliest activity start in the Actual version to that version's update date (8). | Period from the earliest activity start across the project's Actual schedule versions to the earliest update date (8) among those versions. | |
| "Time remaining until forecast finish" (9) | Period from the Actual version's update date (8) to its latest activity finish. | Period from the earliest update date (8) among the project's Actual schedule versions to the latest activity finish across those versions. | |
| "Planned activity start" (10) | Earliest activity start in the Baseline version. | Earliest activity start across the project's Baseline schedule versions. | |
| "Baseline finish" (11) | Latest activity finish in the Baseline version. | Latest activity finish across the project's Baseline schedule versions. | |
| "Forecast start" / "Actual start" (12) | Earliest activity start in the Actual version. | Earliest activity start across the project's Actual schedule versions. | |
| "Forecast finish" / "Actual finish" (13) | Latest activity finish in the Actual version. | Latest activity finish across the project's Actual schedule versions. | |
Schedule analytics also automatically calculate the forecast lead or delay relative to the plan (14), expressed in days as the difference between planned and forecast duration. The percentage chart (15) shows progress relative to the planned duration. The value is calculated as follows:
Schedule Analytics for Projects, Schedules, and Versions
Cost Analytics for Projects, Project Groups, and Schedules
To configure cost analytics, select the required node in the Enterprise Project Structure (1) and open "Node settings" (2).
Opening Node Settings
In the node settings window, open "Analytics" (1), click "Add" (2), enter a name for the configuration (3), and click "Add schedule" (4). Select the required schedule from the drop-down list (5), specify the planned cost value in "Plan" (6) and the actual cost value in "Actual" (7), then click "Save" (8). By default, project cost analytics use the Planned Cost and Actual cost attributes.
Configuring Project Cost Analytics
After saving the configuration, click "Activate" (1). Its status changes to "Active". Then close "Node settings" (2).
Activating the Cost Analytics Configuration
Cost analytics (1) become available when you select a Project, Project Group, Schedule, or Version node in the Enterprise Project Structure (2). At the Project Group and Project levels, cost metrics are aggregated from the costs of activities in their schedules.
Cost analytics display the following metrics:
- Plan (3) — Total value of the planned cost attribute from the Baseline schedule version (4).
- Forecast (5) — Total value of the planned cost attribute from the Actual schedule version (6).
- Actual cost incurred (7) — Total value of the actual cost attribute from the Actual schedule version.
- Forecast remaining cost (8) — Difference between Forecast (5) and Actual cost incurred (7).
Cost analytics also automatically calculate the variance between forecast and planned cost (9). The percentage chart (10) shows budget utilization relative to forecast cost. The value is calculated as follows:
Cost Analytics for Projects, Project Groups, and Schedules
You can add an S-curve to the "Analytics" tab to monitor project cost metrics. Open the project settings, select "Analytics" (1), and click "Add S-curve" (2) in "S-curve settings". In the "Analytics settings" dialog, specify the configuration name (3), calculation type (4), and calculation parameters (5).
The following calculation types are available:
- Activity attributes — Displays selected schedule activity attributes on the S-curve.
- Daily planning — Displays schedule daily planning parameters on the S-curve.
The saved parameters appear in "S-curve settings" (6).
Click the eye icon next to an S-curve name (7) to hide it from the "Analytics" tab of the EPS element being configured. Click the visibility button again to display the widget.
Configuring an S-Curve
The configured S-curve (1) appears on the "Analytics" tab with the selected parameters. The widget displays three curves for comparison: plan, actual, and baseline plan. Select "Display as percentages" (2) to display the parameters as percentages.
S-Curve on the Analytics Tab
Work Quality Analytics for Projects and Schedules
Quality analytics (1) become available when you select a Project or Schedule node in the Enterprise Project Structure (2). Project-level metrics are aggregated from the quality of activities in the project's schedules.
Quality analytics display the following metrics:
- Issues raised (3) — Number of requests or assignments in the schedule.
- Issues resolved (4) — Number of accepted requests or assignments in the schedule.
- Activities started (5) — Number of activities with the In progress or Completed status.
- Activities not started (6) — Number of activities with the Not started status.
- Activities performed without issues (7) — Number of Completed or In progress activities without requests or assignments.
- Activities performed with issues (8) — Number of Completed or In progress activities with requests or assignments.
The percentage chart (9) shows the level of work quality.
Quality is classified as follows:
- Low quality: Below 30%.
- Medium quality: From 30% through 70%, inclusive.
- High quality: Above 70%.
The value is calculated as follows:
Work Quality Analytics for Projects and Schedules
Activity Count and Status Analytics for Projects, Schedules, and Versions
Activity count and status analytics (1) require no special configuration and are available at the Project, Schedule, and Version levels when you select the corresponding EPS node (2). Project-level data are aggregated from the Actual versions of the project's schedules.
Activity Progress Analytics for Projects, Schedules, and Versions
Project Indicator Analytics for Projects and Schedules
Analytics for configured indicators are available when you select a Project or Schedule node in the Enterprise Project Structure. PLAN-R displays the indicator name (1), the linked schedules (2) for which indicator rules are configured, and the number of indicators in different states on activities in each schedule (3). When you select a Schedule node, PLAN-R also displays each schedule's role in the configured pair: main or supporting. For details about configuring project indicators and schedule links, see Configuring Indicators.
Project Indicator Analytics for Projects and Schedules
Additional Project Group Analytics
Selecting a Project Group node displays the following additional metrics:
- Summary information about the number and status of projects in the group (1).
- A breakdown of total cost by project over time, displayed as a column chart (2).
Project Group Analytics: Project Status and Total Cost Distribution
- A breakdown of cost incurred by project over time, displayed as a column chart.
- Interactive views for ranking projects within the group (1).
Projects can be ranked by the following criteria:
- Schedule:
- Duration (days);
- Project completion (%);
- Project duration variance (days);
- Project duration variance (%);
- Activity start variance (days);
- Activity finish variance (days).
- Cost:
- Budget (RUB);
- Budget variance (RUB);
- Budget variance (%);
- Budget utilization (RUB);
- Budget utilization (%).
To rank projects in the interactive view, select the ranking category, schedule or cost (2), specify the metric source (3), and, if needed, sort the project list in ascending or descending order (4).
Project Group Analytics: Cost Incurred and Project Ranking
Additional Schedule Metrics
Selecting schedules in the Enterprise Project Structure displays the following additional analytics:
- An interactive table with physical volume completion metrics based on the Actual version, Baseline version, and daily plans (1).
If only one schedule version has been created, the physical volume completion table is displayed in "Analytics". If the version contains no data for analytics, "No data" appears at the bottom of the table.
The table contains the following metrics:
- Physical volume name;
- Unit of measure;
- Total — Total planned physical volume across all schedule activities.
- Expected completion — Physical volume expected to be completed if activities follow the dates in the Actual schedule version.
- Actual completion — Total actual physical volume across all schedule activities.
- Variance — Difference between expected and actual completion.
- Expected % — Ratio of expected completion to total planned physical volume in the schedule.
- Actual % — Ratio of actual completion to total planned physical volume in the schedule.
- Indicator, with the following possible colors:
- Green if Expected % is less than or equal to Actual %;
- Red if Expected % is greater than Actual %;
- Blue if Actual % is greater than or equal to 100;
- White if Actual % is less than or equal to 100.
Schedule Analytics: Physical Volume Completion
The table supports ascending and descending sorting by any metric except Indicator. Left-click a column heading to sort its values.
Updating Analytics Data
PLAN-R automatically refreshes the analytics data used by widgets within 5 minutes. To retrieve current data immediately, click "Refresh analytics" (1).
Refreshing Analytics Data for Widgets
Comparing Schedule Versions
To compare attribute values across schedule versions, select a Schedule node in the Enterprise Project Structure (1), open "Analytics", and click "Compare versions" (2). In the dialog, select the schedule versions (3) and, if needed, specific attributes to compare (4), then click "Run" (5).
The results area displays activities with differing values for the selected attribute (6). Activities are matched by code (7). Click "Export to file" (8) to save the comparison results in XLSX format.
Comparing Schedule Versions
Configuring and Printing Analytics
PLAN-R allows you to configure analytics widget views for individual users and create global views available to all users in the space. To create a view, open "Analytics" (1), click "Analytics settings" (2), and open the view "Settings" (3).
Opening Analytics View Settings
The "Analytics settings" dialog contains the following tabs:
- All (1) — Displays existing analytics configurations.
- My (2) — Creates configurations for the active account.
- Global (3) — Creates a view available to all users in the space.
Click "+Add view" (4), enter a name for the new view (5), and click "Create" (6) to save it.
Configuring an Analytics View (1)
Select the analytics view to configure (1), select a node (2), configure dashboard visibility (3), and click "Save" (4). Click "Activate" (5) to activate the analytics view. This button is available both on the view creation tab and on "All" (6).
Configuring an Analytics View (2)
To print analytics, open "Enterprise Project Structure" (1), select "Analytics" (2), and choose a Project Group, Project, or Schedule element (3). Click "Print analytics" (4). The downloaded .zip archive contains analytics for the selected element.
Printing Analytics