RESOURCE BREAKDOWN STRUCTURE
A Resource Breakdown Structure (RBS) is a hierarchical model for creating a multilevel structure of resources required to perform project activities. It is created from resource directories and follows a hierarchy similar to the Work Breakdown Structure (WBS), with a focus on resources rather than tasks.
The parent resource coefficient is a key parameter in this model. It determines how many units of a child resource are required per unit of its parent. This coefficient is used to calculate the child resource’s planned quantity based on the parent resource requirement. The coefficient is recalculated when the child resource’s planned quantity changes.
Creating a Resource Breakdown Structure
To create an RBS, open “Directory library” (1), select its scope (2), open the “RBS” tab (3), and click “Add” (4). In the window that opens, enter the RBS name (5) and click “Create” (6).
Creating an RBS (1)
Click “+ Add a entry” (1) in the contents area to open a window where you can select the entry type:
- Resource (2) — creates an entry by selecting a resource from a resource directory;
- Resource group (3) — a planning tool representing an abstract collection of resources sharing a particular characteristic. Assigning a resource group to an activity records the project’s overall resource requirement without specifying individual resources, providing flexibility during early planning. A new group entry is created manually.
Selecting “Resource” activates the resource directory field (4). Its drop-down list contains all available PLAN-R resource directories. The “Members” system directory (see “Members Directory”) is also a resource directory, so its entries can be used in the RBS hierarchy. Click “Resource name” (5) to select a resource from the directory.
Creating an RBS (2)
The window that opens displays the resource directory contents. To select one or more resources, select their checkboxes (1) and click “Assign” (2).
Creating an RBS (3)
When you select “Resource group”, enter a resource name (1) and specify a unit of measure (2). Select the unit from the drop-down list populated from the “Units of Measure” system directory.
When creating a resource hierarchy within a group, units of measure must be consistent. All child entries belonging to the same parent group must use the same unit of measure.
Creating a Resource group in an RBS
To populate a resource group, click “± Add child entry” (1). In the window that opens, select “Resource” (2) or “Resource group” (3), then select a directory (4) and resource (5).
Populating a Resource group in an RBS (1)
The window that opens displays the resource directory contents. To select one or more resources, select their checkboxes (1) and click “Assign” (2).
Populating a Resource group in an RBS (2)
Initially, a resource group has a question mark icon (1). After you add one or more resources with matching units of measure, the icon automatically changes to represent the corresponding resource type: material, labor, cost, or nonlabor (2).
Populating a Resource group in an RBS (3)
Resource Type Symbols
| Resource type | Icon |
|---|---|
| Cost | ![]() |
| Labor | ![]() |
| Material | ![]() |
| Nonlabor | ![]() |
| Resource group |
,
,
,
,
|
To change the resource linked to a resource group entry, double-click one of its resource attributes (1): Name, Resource code, or Unit of measure. In the window that opens, select another resource directory (2) and resource (3). Click “Save” (4) to replace the previous resource in the RBS row with the new one.
Editing a resource group entry’s resource link
Assigning Resource Breakdown Structure Rows to Schedule Activities
An RBS is used in PLAN-R when the schedule is in “Resource planning” mode (1).
To assign an RBS row, select a schedule activity (2) and click “Add resource” (3). In the window that opens, select an RBS (4) and resource (5). You can also enter assignment attribute values (6): “Consumption curve” (see “Consumption Curves”), “Plan”, and “Actual”.
Select “Controlling Resource” (7) to designate the assigned resource as the key resource that directly determines activity duration. Its usage rate sets the pace of work and affects the activity’s overall duration. For example, a crane is the Controlling Resource for “Structural Installation”. Its “Units/time” value—for example, how many elements it can lift in one working hour—determines its work duration.
If “Calculate plan by units/time” (8) is selected, the resource’s planned quantity is calculated automatically by multiplying its units/time by the activity’s work duration in hours. For hierarchical resources, the plan is calculated only for the parent resource. Planned quantities for child resources are distributed according to the parent resource coefficient.
To assign one resource to multiple activities at once, first select the activity checkboxes, then click “Add resource”.
Attention! A resource from a Resource directory cannot be assigned without an RBS. To assign a single resource without a hierarchy, add it to an RBS, then assign (9) that RBS resource to the schedule activity.
Assigning an RBS row to a schedule activity
Assigning a Resource group (1) to a schedule activity lets you allocate resource requirements provisionally without specifying individual resources. This provides flexibility during early planning. A group can contain different resources, including specific assignees from the “Members” directory. For example, you can assign a “Labor resource” group to record the project’s overall requirement for a particular specialization, then replace the group with a specific employee at a later stage.
Assigning a resource group to a schedule activity
To specify the resource later, select the assigned resource group (1) in the resource planning table and click “Replace resource” (2). In the window that opens, select an RBS entry (3) and click “Assign” (4).
Replacing a resource group with a specific resource
To remove an RBS entry from resource planning, select a schedule activity (1), select the RBS entry (2) in the table, and click “Delete resource” (3). To remove an RBS entry from multiple activities at once, first select the activity checkboxes, then click “Delete resource”.
Bulk resource assignment and removal require permissions F3.2.3.10.1.1, “Bulk resource assignment”, and F3.2.3.10.2.2, “Bulk resource assignment removal”.
Removing an RBS row assigned to a schedule activity