CONSUMPTION CURVES

Resource consumption curves allow you to distribute a resource quantity unevenly over an activity’s duration. You can specify the percentage of the total resource quantity to be consumed in each period between the activity’s start and finish, with periods expressed as percentages of work duration.

Consumption curves are used when distributing resources (see “Daily Distribution of Planned and Actual Values in Simplified Planning” and “Daily Plan Distribution in Resource Planning”). They help you:

  • Model actual resource workloads—for example, specify higher usage at the beginning, middle, or end of an activity according to the process;
  • Manage cash flow and personnel workloads by accounting for actual peaks in personnel or equipment usage;
  • Automatically distribute the remaining resource quantity—PLAN-R distributes the unused quantity according to the selected curve;
  • Improve planning accuracy, particularly for irregular or cyclical activity profiles where an even distribution does not reflect actual usage.

You can create consumption curves at any level of the Enterprise Project Structure if you have permission F2.2.2.6, “Edit Consumption Curves”. Custom and system curves are inherited from parent nodes by their child nodes. To configure a consumption curve, select any node (1) in the Enterprise Project Structure, open “Node settings” (2), and go to the “Resource consumption” tab.

register imageOpening Enterprise Project Structure node settings

PLAN-R provides the following predefined system consumption curves:

  1. “Linear” — uniform resource consumption throughout the activity. Each 5% interval, except the 0% point, has a weight of 5%, totaling 100%.
  2. “Progressively Increasing Triangular” — resource usage gradually rises to a peak at approximately 65–70% of the duration, then gradually decreases while remaining above its initial values. Typical of processes with a ramp-up followed by a decline.
  3. “Peak–Plateau” — a rapid increase at the start to high values at 10–11% of the duration, followed by a sharp drop to zero in the middle and another rise to a plateau at the end. Represents two intensive activity phases separated by a pause.
  4. “Front-Loaded” — high resource consumption during the first half of the activity, approximately 6.5% per interval up to 50% of the duration, followed by a sharp decrease to approximately 3.5% during the second half. Used for activities with an accelerated start.
  5. “Back-Loaded” — lower resource consumption during the first half, 3.5% per interval, followed by higher consumption of 6.5% after 50% of the duration. Suitable for activities whose main workload occurs closer to completion.
  6. “Bell-Shaped” — a symmetrical resource consumption curve with a peak in the middle, 12% per interval at 40–60% of the duration, and a gradual decline toward the ends to 0.5%.
  7. “Shifted Triangular” — resource consumption rises to a maximum at approximately 65–70% of the duration, followed by a more gradual decline. Similar to the progressively increasing curve, but with a less pronounced second half.
  8. “Normal (S-Curve)” — resource consumption starts slowly, accelerates in the middle with a peak of 14% at 45–55% of the duration, then slows down. A typical profile for projects where resources are introduced gradually.
  9. “Decreasing Triangular” — maximum resource usage at the start, 9%, followed by a steady decline to 1% at the end. Suitable for activities requiring high output immediately.
  10. “Double Peak” — two symmetrical peaks: the first at approximately 30% of the duration, 10%, followed by a decline, and the second at approximately 70%, also 10%. Suitable for processes with two distinct phases of activity.
  11. “Early Peak” — resource consumption quickly rises to a maximum of 10% at 30–40% of the duration, then gradually decreases to 1% at the end. Typical of activities with a critical start.
  12. “Triangular” — resource consumption rises toward the middle, peaking at 9% at 45–55% of the duration, then decreases symmetrically.
  13. “Three-Step” — three resource consumption levels: initially moderate, 4% per interval; then higher in the middle, 6.5% per interval; and finally moderate again, 4% per interval. Represents stages with different usage rates.
  14. “Trapezoidal” — resource consumption gradually rises to a plateau of 7.5% per interval at 35–70% of the duration, then decreases symmetrically. Provides an extended period of stable resource usage.
  15. “Increasing Triangular” — resource consumption rises from 1% at the start to 9% at the end. Unlike “Decreasing Triangular”, usage increases toward the finish.

To create a custom consumption curve, click “Add” (1). In the window that opens, enter a name (2) and, if needed, select an existing consumption curve as a template (3).

The Y-axis shows the resource consumption percentage (4), with a maximum value of 100%.

The X-axis shows the percentage of work duration (5), from the activity’s start at 0% to its finish at 100%, in 5% increments. You can specify a resource consumption percentage (6) for each of these 21 intervals. The total of all entered consumption percentages is also displayed (7):

  • If the total is below or above 100, PLAN-R proportionally scales the values to total 100% when you save the settings;
  • If the total exceeds 100, the number is highlighted in red to warn that the maximum consumption percentage has been exceeded.

As you enter a resource consumption percentage for each duration interval, PLAN-R automatically plots a curve (8) showing cumulative resource consumption over the activity’s duration. Click “Save” (9) to save the settings.

register imageCreating a consumption curve