ACTIVITY INDICATORS

Activity indicators (1) are created within a single schedule using its activity attributes or user-defined values and indication rules. These indicators are not displayed on the Gantt chart. They are displayed as activity attributes whether the schedule is opened as the General Schedule or the Support Schedule.

register imageActivity indicators

Configuring Activity Indicators

To open the activity indicator settings, select a Schedule node (1) in the Enterprise Project Structure and click “Node settings” (2).

register imageOpening the schedule settings menu

In the window that opens, go to the “Tasks indicators” section (1). Click “Add” (2) to create a new indicator.

register imageAdding an activity indicator

In the next window, enter the indicator name (3), specify its shape (4), and select the color (5) to display when the rule is met. To define an indication rule, click the “+” button (6) and specify the conditions used to calculate the indicator:

  • first parameter: an attribute from this schedule to use in the logical expression (7);
  • operator, selected from the drop-down list of available logical operators (8);
  • source of the second parameter, selected from the drop-down list of available options (9);
  • second parameter: an attribute to use in the logical expression, if required (10).

The second parameter in a color condition’s logical expression can be:

  • an activity attribute from this schedule;
  • the current date;
  • the schedule’s update date;
  • a number;
  • a user-defined date.

To check conditions against the previous row, activate the corresponding button (11). To combine multiple conditions within a single rule, click the “AND” or “OR” operators (12). To add multiple indicator calculation rules, click “Add condition” (13).

Rules are checked from top to bottom. Once a rule is met, the remaining rules are not checked. To change the order in which rules are checked, use the move buttons on the right (14).

You can copy indicator settings by exporting them to a file and importing them. To export the indicator settings, click “Export in file” (15) in the corresponding window. To apply previously exported settings, click “Import from file” (16) and upload the file containing the settings.

The “Display on «Analytic» tab” checkbox (17) is selected by default so that configured indicators appear on the “Analytics” tab in the Enterprise Project Structure. To save the activity indicator settings, click “Save” (18).

After you save the settings, PLAN-R automatically calculates the configured indicator.

register imageConfiguring an activity indicator

Displaying Activity Indicators

Configured activity indicators cannot be displayed on the Gantt chart, but they can be displayed on activities in the General Schedule and Support Schedule. The activity indicator (1) will be available for display in the “Indicators” section of the view settings menu.

register imageDisplaying activity indicators