LINK INDICATORS
Link indicators are created between different project schedules using their attributes or user-defined values and indication rules. These indicators appear on the Gantt chart (1) and can also be displayed in the Work Breakdown Structure (2) and on activities in the Support Schedule (3).
Indicators in the General Schedule and Support Schedule
Configuring Link Indicators
To open the link indicator settings, select a Project node (1) in the Enterprise Project Structure and click “Node settings” (2).
Opening the project settings menu
Next, open the “Links indicators” section (1), click “Add” (2), and configure the indicator by specifying the following parameters:
- indicator name (3);
- link, selected from the schedule pairs previously configured for the project (4);
- date displayed: a date attribute from the Support Schedule used to position the indicator on the Gantt chart (5);
- shape, selected from the drop-down list of available indicator shapes (6);
- color conditions: click “Add condition” (7) and specify:
- source of the first parameter: select a schedule from the pair associated with the selected link (8);
- first parameter: an attribute from the selected schedule to use in the logical expression (9);
- operator, selected from the drop-down list of available logical operators (10);
- source of the second parameter: select a schedule from the pair associated with the selected link, or select “Update date”, “Date”, “Empty”, “Number”, “String”, or “Current date” (11);
- second parameter: an attribute from the selected schedule or a value to use in the logical expression (12);
- indicator color to display when the condition is met (13);
- priority: select the condition that takes priority when several Support Schedule activities have different indicator colors. This determines the indicator displayed on the Gantt chart and on the General Schedule activity (14).
Conditions are checked from top to bottom. Once a condition is met, the remaining conditions are not checked. To change the order in which conditions are checked, use the move buttons to the right of each condition (15).
The “Display on Gantt chart” checkbox (16) is selected by default. If you clear it, the “Date displayed” field becomes inactive. The configured indicators are no longer displayed on the Gantt chart but remain visible in the Work Breakdown Structure.
The “Display on «Analytic» tab” checkbox (17) is selected by default. If you clear it, the indicators are not displayed on the “Analytics” tab when a Project or Schedule node is selected.
Configuring link indicators
You can change the display order of indicators by dragging them into the required order with the left mouse button.
To calculate an indicator, click “Calculate” (1). If all required settings fields are filled in and the indication rules are configured correctly, the “Calculated” status appears (2). Otherwise, the “Invalid” status appears, indicating that errors in the settings need to be corrected. To calculate all project indicators at once, click “Calculate all” (3).
Calculating a link indicator
When data affecting an indicator’s calculation changes in PLAN-R—for example, after schedule calculation or changes to activity dates or attribute values used in an indicator condition—the indicator’s status automatically changes from “Calculated” to “Calculate”. The indicator is then unavailable for display in the schedule workspace. In this case, recalculate the configured indicator as described above.
Displaying Link Indicators
Configured link indicators appear on the Gantt chart by default and can also be displayed on activities in the General Schedule and Support Schedule. To display them, open the view settings for each schedule and expand the list of available attributes in the “Indicators” category (1). Drag the required indicator into the active view (layout), or double-click it.
Displaying link indicators