CREATING, DELETING, AND MODIFYING ENTERPRISE PROJECT STRUCTURE NODES
The Enterprise Project Structure can contain the following node types:
- Space;
- Project Group;
- Project;
- Schedule Group;
- Schedule;
- Registry (see Node Display Mode).
The following restrictions apply when creating the Enterprise Project Structure:
- The root node must be of the Space type and may contain child nodes of the Project Group and Project types.
- A Project Group node may have child nodes only of the Project Group and Project types.
- A Project node may have child nodes of the Schedule Group, Schedule, and Registry types.
- A Schedule Group node may have child nodes of the Schedule Group, Schedule, and Registry types.
- A Schedule or Registry node may contain Version elements and may not contain any other child nodes.
To create a node (Project Group, Schedule Group, Project, Schedule, or Registry), select its parent node and click "Add node/version" (1) on the enterprise configuration toolbar. When creating a Project, Schedule, or Registry node, use the checkboxes in the dialog to configure automatic creation of an Actual schedule version and whether it should open automatically afterward.
To reposition nodes within the Enterprise Project Structure, select the required node and use "Move up" and "Move down" (2), or "Move left" and "Move right" (3), on the enterprise configuration toolbar.
To copy or move a project to another node, click "Copy project" (4) or "Cut" (5). Then select a Space or Project Group node and click "Paste project" (6). The schedule's planning mode settings are retained (see Planning in PLAN-R for details).
To delete a node from the Enterprise Project Structure, select it, click "Delete" (7), and click "Delete" in the confirmation dialog. To delete multiple nodes, click "Select using checkboxes" (8) to display the checkboxes, select the nodes to delete (9), and click "Delete by checkboxes" (7).
To rename a node, select it in the Enterprise Project Structure and click "Node settings" (10) on the enterprise configuration toolbar. Edit the node name in the dialog and click "Save".
Creating, Configuring, and Deleting Enterprise Project Structure Nodes
To rename a Schedule Group node, select it (1) in the Enterprise Project Structure, right-click it, and select "Rename" (2). Edit the name in the input field (3). Press Enter or click "Save" (4) to save the changes.
Renaming a Schedule Group Node
To move a Schedule node, select it (1) in the Enterprise Project Structure, right-click it, and select "Move to group" (2). Then select a Schedule Group (3) from the drop-down list.
Moving a Schedule Node to a Schedule Group Node
Each added schedule version can be assigned one of the following statuses:
- Actual — The current schedule version used when working with the project. Only one version per schedule can have this status.
- Baseline — The schedule version whose dates are used as the project's target dates. Only one version per schedule can have this status.
- Version — An archived schedule version. There is no limit to the number of archived versions within a schedule.
PLAN-R allows you to change a schedule version's status at any time. Select the schedule version in the Enterprise Project Structure (1), click the button displaying its current status on the enterprise configuration toolbar (2), and select a new status from the drop-down list (3).
Configuring the Schedule Version Status