CREATING AND ASSIGNING CALENDARS

System and custom calendars are located in "Calendars" (1). This section has two resizable areas: the Enterprise Project Structure on the left and the calendar list on the right. When a space is created, the system calendar "PLAN-R: 7 days" (2) is created automatically. It uses a seven-day working week with eight working hours per day: 9:00 a.m.–1:00 p.m. and 2:00–6:00 p.m. Its settings cannot be edited. The calendar is marked "System" (3). Calendar creation and editing permissions can be configured for roles (see Permissions for Calendars).

Calendars can be created on any structure node, with no limit on their number. A custom calendar is available for assignment to activities in all schedule versions below the node where it was created. Deleting an EPS node also deletes calendars created within that structure.

Selecting a node displays all available calendars on the right. Calendars created on a higher-level node have an "Inherited" label (4), whose color matches the parent node. Click the label to navigate to that node. Custom calendars created on the selected node can be edited and deleted.

The "Default" label (5) identifies the calendar assigned automatically when an activity is created in the interface or when an imported schedule version contains no calendar information.

register imageCalendars Section

Creating a Calendar

Open "Calendars" (1), select a structure node (2), and click "Add" (3).

register imageAdding a Calendar

The "Calendar" window provides:

  • Name (1) — Calendar name;
  • Weekly scale (2) — A five-day working week by default, with Saturday and Sunday as nonworking days;
  • Yearly scale (3);
  • Calendar date area (4);
  • Cancel (5);
  • Delete (6);
  • Set as default (7) — Assigns the calendar as the node's default; only one default calendar can be assigned to a node;
  • Save (8).

register imageCreating a Calendar

Configuring Working Hours

Working hours are configured in "Working time settings".

Select a day on the weekly scale. The dialog displays the selected weekday (1), hours (2), and minutes (3).

Working periods are 9:00 a.m.–1:00 p.m. and 2:00–6:00 p.m. by default. For a nonworking day, all periods initially appear as nonworking.

Left-click to select a single 15-minute block. Hold Shift while clicking to select a continuous range (4). Colors indicate:

  • Gray — Nonworking period (5);
  • White — Working period (6).

The dialog provides two options:

  • Set all periods as working (7) — Applies to the selected weekday throughout the year. The day appears white on the weekly scale and in the calendar date area.
  • Set all periods as nonworking (8) — Applies to the selected weekday throughout the year. The day appears gray.

Select "Apply to working days" (9) to apply the settings to all working days of the week.

Click "Cancel" (10) to discard changes.

Click "Save" (11) to apply them.

register imageWorking Time Settings

To create a working-time exception for a specific date, left-click the date in the calendar (1), configure its working hours (2), and select:

  • Annual exception — Applies to all years; the date appears light green (3).
  • One-time exception — Applies to the current year; the date appears green (4).

Nonworking-time exceptions are configured in the same way. Annual nonworking exceptions appear light red (5), and one-time exceptions appear red (6).

Click "Save" (7).

register imageConfiguring a Working-Time Exception for a Calendar Date

Assigning Calendars to Activities and Work Packages

You can assign a calendar to a selected schedule activity (1) by:

  • Selecting a value for Calendar (2) from the drop-down list (3) in the WBS;
  • Selecting a calendar in the corresponding control (4) or the full attribute list (5) on "Activity card" (6).

The assigned calendar is used during subsequent schedule calculations to determine activity durations and dates. Newly created activities use the default calendar.

A newly created node inherits its parent's default calendar. For example, if Project uses calendar A by default, a new Schedule node also uses A until the user selects another calendar (3, 4, or 5).

register imageAssigning Calendars to Schedule Activities

Assign a calendar to a work package in the same way by selecting that package. The calendar applies to all activities within it. Selecting the top-level work package allows you to assign a calendar to the entire schedule.

If an imported version does not specify a calendar, activities receive the default calendar.

Permissions for Calendars

PLAN-R provides permissions to protect calendar settings and control changes:

  • Assigning a default calendar;
  • Adding, editing, and deleting calendars.

Assign default calendar allows users to set the default calendar for any node. Without this permission, the setting is read-only.

Configure calendars allows users to create and delete calendars on the selected node. Without this permission, adding calendars and editing existing ones are unavailable.

Permissions are assigned in role settings in "Administration". Open "Enterprise Project Structure" (1) and select "User settings" (2).

register imageConfiguring Protection Against Calendar Changes

On "Roles" (3), select the required role (4), configure permissions using the checkboxes (5), and click "Save" (6). Calendars controls whether the section appears on the navigation bar and can be opened.

register imageConfiguring Protection Against Calendar Changes: Roles