CONFIGURING LINKS BETWEEN SCHEDULE ACTIVITIES
Select "Activity links" (1) from the drop-down list on the right side of the Schedule view. The selected schedule is displayed on the right by default. When you select an activity on the left, its predecessor in the current schedule version is highlighted in red on the right, and its successor is highlighted in green.
To create links between activities in one or more schedules, specify:
- Link creation scenario: Consistent or Group (2);
- Relationship direction: Predecessor or Successor (3);
- Link type (4);
- Lag (5).
The following link types are supported:
- Finish-to-Start — With zero lag, the successor starts after the predecessor finishes.
- Start-to-Start — With zero lag, the successor starts at the same time as the predecessor.
- Finish-to-Finish — With zero lag, the successor finishes at the same time as the predecessor.
- Start-to-Finish — With zero lag, the successor finishes before the predecessor starts.
Lag is a numeric value specified in days or hours, depending on the schedule's time resolution. The successor activity's calendar is used when calculating lag. Positive lag delays the successor relative to the predecessor, shifting it to the right on the timeline according to the link type. Negative lag represents a lead, shifting the successor to the left.
To create a single link, select an activity on the left, choose Consistent, select the activity to link on the right, and click "Link" (6). To create multiple links, select an activity on the left, choose Group, click "Record" (7), and left-click the required activities on the right one after another. Click "Record" again when finished.
Use search (8) and displayed attribute settings (9) to find an activity. Click "Enterprise Project Structure" (10) to open another schedule. Use the corresponding button (11) to return to the current schedule version.
Configuring Activity Links (1)
You can also create links through "Services" (1). Click "Create link" (2) to create sequential links between selected activities (3), (4).
Click "Link activities by checkboxes" (5) to create Finish-to-Start links between checked activities, following their order in the schedule version.
Click "Delete links" (6) to remove links for selected activities. To select a range, hold Shift and click its first and last activities in the numbering column (7). To select individual activities, hold Ctrl while selecting them in that column.
Configuring Activity Links (2)
Links can also be created on the Gantt chart. Select an activity (1), then click "+" before it for a Start-to-Start link (2), or after it for a Finish-to-Start link (3). The link appears as a blue arrow on the chart (4) and on the "Activity links" tab. To delete a link, select it on the Gantt chart and click the trash button (5).
Configuring Activity Links on the Gantt Chart
The "Activity links" tab (1) in the workspace displays existing links. You can add predecessors and successors and change link types. To add a predecessor, click "Add predecessor" (2) on the left and select an activity code from the drop-down list (3). Finish-to-Start (FS) is used by default. Successors are added in the same way on the right.
The activity link table may display the following indicators:
- Critical path (4) — The linked activity is on the critical path.
- External link (5) — The activity is linked to activities in another schedule.
- Managing relation (6) — Free float for the activity link equals zero.
- By beyond logic (7) — At least one of the following conditions is met:
- For predecessors:
- Early start is later than the selected activity's Start.
- Early finish is later than the selected activity's Finish.
- For successors:
- Early start is later than the successor activity's Start.
- Early finish is later than the successor activity's Finish.
- For predecessors:
Attention! Changing an activity's type to Summary activity or WBS node deletes all its predecessor and successor links.
Use "View" (8) to configure displayed attributes, such as Early start (9) and Early finish (10). Click "Go to activity" (11) to navigate to a linked activity. To delete a link, click "Delete links" (12), then "Delete" in the confirmation dialog.
Activity Links Tab in the Workspace
To view predecessor or successor chains for one or more activities, select their checkboxes (1), click "System filters" (2), and select "Work chains" (3). Configure:
- Direction
- Predecessors (4) — Shows incoming links for selected activities.
- Successors (5) — Shows outgoing links for selected activities.
- Chain depth
- Show all (6) — Shows all link levels without a depth limit.
- Level (7) — Shows links up to the specified level, from 1 to 10.
Click "Apply" (8). Checked activities retain their original colors on the Gantt chart (9), while other activities in the chain appear in a paler shade (10). Click "Reset" (11) or "Clear filters" (12) to remove the chain filter.
Work Chains Filter
To display activities with external links, click "System filters" (1) and select "Show activities with external links" (2). Only activities with cross-project links are displayed on the Gantt chart (3). Select "Show activities outside logic" (4) to display only activities with at least one predecessor carrying the By beyond logic indicator (5).
Filters for Activities Outside Logic and Activities with External Links
PLAN-R provides Dissolve activity to preserve connections when an activity is deleted. Select the activity to remove (1), open "Services" (2), and click "Dissolve activity" (3).
The activity is deleted, and links between the remaining activities are created as follows:
- The new link type combines the first letter of the predecessor-to-deleted-activity link type with the second letter of the deleted-activity-to-successor link type.
- The new lag equals the sum of the two original link lags.
- If the deleted activity has multiple predecessors or successors, the number of new links equals the number of predecessor links multiplied by the number of successor links.
Dissolving an Activity