RESOURCE PLANNING

Resource planning is the process of identifying, allocating, and monitoring resources required to perform activities. It is used by companies that already maintain an enterprise resource database and need more detailed planning when aggregate metrics—physical volume, labor units, and cost—are no longer sufficient for effective management.

You can add resources to directories in the “Directory library” section (see “Directories”).

You can also create a Resource Breakdown Structure (RBS): a hierarchical model detailing all resources required to perform activities. An RBS follows a principle similar to the WBS but focuses specifically on resources (see “Creating a Resource Breakdown Structure”).

Relationships between parent and child RBS nodes are controlled by the parent resource coefficient. This coefficient specifies how much of a child resource is required per unit of its parent resource.

An RBS can contain individual resources and resource groups. Groups are useful during early planning stages when the specific resource to be assigned is not yet known. An assigned group can later be replaced with a specific resource.

Important: Resources or groups from a directory cannot be assigned directly to schedule activities. They can only be assigned through an RBS.

register imageRBS assignment to a schedule activity

Resource Planning Schedule Structure

The “Resource planning” section contains the following data:

  • Name (1) — resource name;
  • Unit of measure (2) — resource unit of measure;
  • Planned Quantity (3) — planned resource quantity;
  • Actual Quantity (4) — actual resource quantity, calculated as the sum of actual values in daily planned and actual data;
  • Remaining (5) — the difference between planned and actual resource quantities;
  • Undistributed planned quantity (6) — the difference between the resource’s total planned quantity and the total approved plan distributed in daily planned and actual data;
  • Variance (7) — the difference between actual and planned resource quantities;
  • Consumption curve (8) — the resource distribution scenario used when assigning the resource to a schedule activity (see “Assigning Resource Breakdown Structure Rows to Schedule Activities”);
  • Coefficient (9) — the parent resource coefficient specified by the user. It determines how many units of a child resource are required per unit of its parent;
  • Rate (10) — cost per resource unit;
  • Code (11) — unique RBS entry identifier;
  • Resource code (12) — unique resource code from the resource directory;
  • Name of RBS (13) — Resource Breakdown Structure name;
  • Resource type (14) — resource category from the resource directory;
  • Units/time (15) — resource quantity that can be completed in one working hour. The user specifies this value in the directory, RBS, or directly on the schedule activity;
  • Labor constant (16) — person-hours per resource unit, specified by the user;
  • Controlling Resource (17) — select or clear the “Controlling Resource” checkbox;
  • Directory (18) — resource directory name;
  • Calendar (19) — a calendar assigned to specific resources, such as personnel or equipment, defining their availability through working hours, holidays, and shifts. Resource calendars support unique work patterns, including part-time schedules, vacations, and special working hours.

register imageResource planning section

A Controlling Resource is a resource whose units/time affects activity duration. Its quantity and units/time can be used in schedule calculation (see “Annex 2. Schedule Calculation Algorithms for Different Scenarios”). Only one Controlling Resource can be assigned to a schedule activity. It can be of any type: material, labor, nonlabor, or cost.

The selected Controlling Resource automatically appears in the “Activity card” section (1). Its attribute fields cannot be edited manually because their values are synchronized automatically. Changes made to the Controlling Resource in “Resource planning” immediately appear in the “Activity card”.

If Controlling Resource attribute values have been added or changed in the resource directory, click “Synchronize” (2) to update them for the selected activity. To update multiple activities, select their checkboxes (3) in the Work Breakdown Structure, click “Synchronize”, and click “Confirm” in the confirmation window.

register imageSynchronizing Controlling Resource attributes

Data entry in the planning area (1) works the same way as in simplified planning (see “Simplified Planning Schedule Structure”).

register imageEntering values in the planning area in Resource planning mode

In Resource planning mode, the “Daily plan/actual” tab (1) lets you compare planned and actual resource values across all schedule activities. Select a resource from the drop-down list (2) and choose a metric to analyze.

The following options are available:

  • Quantity (3) — displays planned and actual values for the selected resource, as in the planning area;
  • Cost by rate (4) — displays daily resource values multiplied by the resource’s specified rate;
  • Cost by distributed rate (5) — displays daily resource values multiplied by daily rate values;
  • Labor units by labor constant (6) — displays daily resource values multiplied by the labor constant;
  • Labor units by distributed labor constant (7) — displays daily resource values multiplied by daily labor constant values.

register imageDaily plan/actual tab in Resource planning mode

Configuring the Resource Planning Display

The “Daily plan/actual” table is configured in the same way as in simplified planning (see “Configuring the Simplified Planning Display”).

Click “Views” (1) to select an existing resource planning table view (2). To edit a view or create a new one, click “Settings” (3).

register imageConfiguring the Resource planning view (1)

In the window that opens, you can change the view name (1) and use the eye button (2) to configure the display of timeline and resource attributes in the table. Click “Save changes” (3) to apply your changes.

To create a new table view, click “Create” (4), configure the view, and click “Save as new” (5). To activate a view, click “Activate” (6). To delete a view, click the trash button (7).

You can extend the list of attributes available for the resource planning table. Click “Attribute selection settings” (8).

register imageConfiguring the Resource planning view (2)

In the next window, click “Add attribute” (1). Select a previously created custom attribute from the RBS (2) or resource directory (3) (see “Creating Custom Directory Attributes”) using the drop-down list (4), then click “Create” (5).

register imageConfiguring attribute selection

The selected custom attributes become available through “Add attributes to view” (1). In the window that opens, select an attribute from the drop-down list (2), which also includes RBS assignment attributes (see “Resource Breakdown Structure Assignment Attributes”), and click “Add” (3).

register imageAdding an attribute to the resource planning table view

Click “Data and display” (1) to configure the “Resource planning” section using the following checkboxes:

  • Operational plan (2);
  • Actual (3);
  • Approved plan (4);
  • Rate (5);
  • Labor constant (6);
  • Controlling Resource (7);
  • Material resources (8);
  • Labor resources (9);
  • Nonlabor resources (10);
  • Cost (11);
  • Members (12).

The configured view automatically appears at the bottom of the screen (13).

register imageConfiguring the Resource planning display

To navigate the planning area and the “Daily plan/actual” tab, use the buttons for jumping to an activity’s start (1), finish (2), or a specific date (3) within the schedule. You can also navigate to previous (4) and next (5) values in the planning area.

Click “Time unit settings” (6) to select the time intervals displayed in the planning area (7): “Daily”, “Weekly”, “Monthly”, “Quarterly”, or “Yearly”. You can also configure how manually entered values are distributed by day (8): “At start”, “At finish”, or “Evenly”.

register imageNavigation in Resource planning

Daily Plan Distribution in Resource Planning

In resource planning, PLAN-R allows you to distribute the following types of values:

  • Operational plan;
  • Approved plan;
  • Actual.

To distribute planned values by day, select the required activities using their checkboxes (1). On the right side of the “Schedule” screen, select “Daily plan/actual” (2), click “Services” (3), and select “Distribute by periods” (4). You can also access this function through “Services” (3) in “Resource planning”.

In the window that opens, select the distribution mode (5), resource directory (6), resource to distribute (7), and distribution scenario (8), then click “Apply” (9).

The following scenarios are available for daily distribution of planned values in resource planning:

  • By consumption curve — distributes planned values according to the selected consumption curve (see “Consumption Curves”). If a curve was specified when the resource was assigned, that curve takes priority during distribution. You can also select a curve manually. Values are automatically distributed across the activity’s working days in proportion to the curve’s weights;
  • Plan based on actuals, remaining by consumption curve — distributes planned values taking recorded activity actuals into account. The remaining planned values are distributed evenly over the remaining activity period, starting from the date of the last actual value, according to the selected consumption curve;
  • Evenly over a specified period — distributes planned values evenly over a user-defined period;
  • Proportionally to parent resource — distributes planned resource values in proportion to the parent resource’s planned values for the working period.

register imageConfiguring daily distribution of planned activity values in resource planning

Actual values are distributed over a period beginning on the working day after the date of the last recorded actual value. Select the distribution end date, which is excluded from the period, using one of the following options (1):

  • Schedule version update date;
  • Current date;
  • User-defined date.

After selecting an option, click “Apply” (2).

register imageConfiguring daily distribution of actual activity values in resource planning

The daily plan distribution results appear both on the right side of the “Schedule” screen (1) and in the planning area (2).

register imageDaily plan distribution results in Resource planning mode

To copy a daily plan, select the required activity using its checkbox (1), click “Services” (2), and select “Copy daily plan” (3). In the window that opens, select the copy mode (4):

  • “Copy Operational plan to Approved plan” — copies operational planned values to the approved plan;
  • “Copy Approved plan to Operational plan” — copies approved planned values to the operational plan.

Next, select the resource directory (5) and the resource whose data you want to copy (6). Specify the period within which values will be copied (7), then click “Apply” (8).

register imageCopying a daily plan in Resource planning mode

To clear daily planned or actual data in bulk, select the activities whose data you want to clear using their checkboxes (1), click “Services” (2), and select “Delete distribution” (3). In the window that opens, select the daily distribution type (4), resource directory (5), and resource whose data you want to delete (6). Specify the period to clear (7), then click “Delete” (8).

register imageClearing daily planned and actual data in Resource planning mode