SIMPLIFIED PLANNING

In simplified planning, you do not need to assign resources to schedule activities. You can plan an activity by tracking three main overall parameters:

  • Physical volume;
  • Labor units;
  • Cost.

To assign a physical volume to an activity, open “Activity card” (1) and enter the parameters manually:

  • Code (2) — a unique physical volume identifier;
  • Name (3) — a description of the specific measurable volume of work to be completed during the schedule activity;
  • Unit of measure (4) — the unit used to express the physical volume quantity;
  • Units/time (5) — the physical volume that can be completed in one working hour;
  • Rate (6) — the price per unit of physical volume;
  • Labor constant (7) — the person-hours required to complete one unit of physical volume.

You can also add a physical volume by displaying the corresponding attributes (2–7) in the WBS table and entering their values for the activity.

register imageAssigning a physical volume in the Activity card

The specified physical volume units/time affects the activity’s work duration, calculated as follows:

Work duration = Plan - Actual Units/time + Actual duration

To calculate labor units and cost from the assigned physical volume, enable the “Calculate activity labor units and cost based on physical volumes, labor constants, and rates” option (2) when enabling simplified planning (1).

register imageConfiguring labor unit and cost calculations based on the assigned physical volume

Daily planned and actual labor units are calculated in “Resource planning” using the following formula:

Labor units = Physical volume * Labor constant

Daily planned and actual cost is calculated in “Resource planning” using the following formula:

Cost = Physical volume * Rate

When this option is enabled, labor units and cost cannot be entered manually.

If you disable calculation of activity labor units and cost based on physical volumes, labor constants, and rates, you can enter overall values in the “Activity card” or through attributes in the WBS table, then distribute them by day in “Resource planning”.

Simplified Planning Schedule Structure

The “Resource planning” tab at the bottom of the schedule workspace lets you track the selected activity in detail by day and analyze its key metrics: physical volumes, labor units, and cost.

In simplified planning mode, “Resource planning” contains the following data:

  • Name (1) — the physical volume name (“Name”) and its unit of measure;
  • Plan (2) — the overall planned value taken from the “Plan”, “Planned labor units”, and “Planned cost” attributes. If no overall value is specified, the total approved plan for physical volume, labor units, or cost is displayed;
  • Actual (3) — the total approved, unapproved, and rejected actual values entered for the activity’s physical volume, labor units, or cost;
  • Remaining (4) — the difference between the “Plan” column and the total approved actual values for physical volume, labor units, or cost;
  • Undistributed Plan (5) — the difference between the “Plan” column and the total approved planned values for physical volume, labor units, or cost. A positive calculated value is highlighted in yellow to indicate that the plan needs to be redistributed;
  • Variance (6) — the difference between the total approved planned values and total approved actual values before the current date, excluding the current date, for physical volume, labor units, and cost;
  • The area for planning and entering metric values over the selected period (7).

register imageSimplified planning schedule structure

You can enter data in the planning area in the following ways:

  • Enter data in a single cell:
    • Type a value without first activating the cell;
    • Activate the cell (1) by double-clicking it with the left mouse button, then enter a value;
    • Paste a value from the clipboard.
  • Enter values in bulk:
    • Fill values by dragging (2) in PLAN-R. Select a cell or range, hover over the blue square in the lower-right corner of the selection, hold down the left mouse button, and drag to the required area (3);
    • Paste a range of values from the clipboard. You can copy a range from the daily planning interface or from spreadsheet files, such as .xlsx files.

Attention! Pasting values into an area containing existing data overwrites that data. Values are pasted only into the daily planning columns currently displayed on the timeline (see “Configuring the Simplified Planning Display”).

If the pasted range exceeds the number of available rows, values outside the range are ignored, and PLAN-R displays the warning “Values are outside the range”.

Pasting also respects the restrictions on changing data for past periods (see “Entering Actual Data for Plan Distribution”).

To delete values, select the required cell or range and press Delete or Backspace.

register imageEntering values in the planning area in Simplified planning mode

The following metrics can be entered in the planning area:

  • Approved plan (1) — the baseline plan that records the project’s initial values before execution begins;
  • Operational plan (2) — the current plan, which can be adjusted as conditions change during project execution;
  • Actual (3) — the recorded result of activity execution;
  • Labor constant (4) — the person-hours required to complete one unit of physical volume;
  • Rate (5) — the price per unit of physical volume.

register imageSimplified planning metrics

The “Daily plan/actual” tab (1) on the right side of the schedule workspace lets you compare daily planned and actual values across all schedule activities for the metric selected from the drop-down list (2): physical volume, labor units, or cost.

The following options are available for viewing daily planned and actual physical volume values:

  • Quantity (3) — displays planned and actual physical volume values, as in the planning area;
  • Cost by rate (4) — displays daily physical volume values multiplied by the physical volume’s specified rate;
  • Cost by distributed rate (5) — displays daily physical volume values multiplied by daily rate values;
  • Labor units by labor constant (6) — displays daily physical volume values multiplied by the labor constant;
  • Labor units by distributed labor constant (7) — displays daily physical volume values multiplied by daily labor constant values.

For labor units and cost, you can analyze the specified quantities across all schedule activities.

register imageDaily plan/actual tab in Simplified planning mode

Configuring the Simplified Planning Display

To configure the table on the “Daily plan/actual” tab, click “Data and display” (1). In the window that opens, use the checkboxes to select the metrics to display:

  • Approved plan (2);
  • Operational plan (3);
  • Actual (4).

You can also configure the data layout:

  • In rows (5);
  • In columns (6).

The configured view automatically appears on the right side of the screen (7).

register imageConfiguring the Daily plan/actual tab view

To configure the “Resource planning” view in simplified planning mode, click “Data and display” (1). In the window that opens, use the checkboxes to select the metrics to display:

  • Operational plan (2);
  • Actual (3);
  • Approved plan (4);
  • Rate (5);
  • Labor constant (6);
  • Labor resources (7);
  • Physical volume (8);
  • Cost (9).

The configured view automatically appears at the bottom of the screen (10).

register imageConfiguring the Resource planning view

The following display settings are available for the resource planning area and the “Daily plan/actual” tab:

  • Time intervals: daily, weekly, monthly, quarterly, or yearly (1). In the planning area, you can also configure how manually entered values are distributed by day: “At start”, “At finish”, or “Evenly”;
  • Navigation to previous and next values (2);
  • Navigation to the activity’s start date, finish date, or a specified date (3);
  • Display period settings (4).

To keep the “Daily planning” section positioned at the start, finish, or a user-defined date when switching to another activity, right-click “Go to start date”, “Go to finish date”, or “Go to specified date” (3). The active button is highlighted in gray. When you select another schedule activity, “Daily planning” opens at the position corresponding to the active button.

To disable this behavior, right-click the button again.

Left-clicking “Go to start date”, “Go to finish date”, or “Go to specified date” (3) navigates to that date once. It does not retain the selected viewing position for other schedule activities.

register imageConfiguring the resource planning area display

Daily Distribution of Planned and Actual Values in Simplified Planning

In simplified planning, PLAN-R allows you to distribute the following types of values:

  • Operational plan;
  • Approved plan;
  • Actual.

To distribute planned values by day, select the required activities using their checkboxes (1). On the right side of the “Schedule” screen, select “Daily plan/actual” (2), click “Services” (3), and select “Distribute by periods” (4). You can also access this function through “Services” (3) in “Resource planning”.

In the window that opens, select the distribution mode (5), the items to distribute (6), and the distribution scenario (7), then click “Apply” (8).

The following scenarios are available for daily distribution of planned values in simplified planning:

  • By consumption curve — distributes planned values according to the selected resource consumption curve (see “Consumption Curves”). Values are automatically distributed across the activity’s working days in proportion to the curve’s weights;
  • Plan based on actuals, remaining by consumption curve — distributes planned values taking recorded activity actuals into account. The remaining planned values are distributed evenly over the remaining activity period, starting from the date of the last actual value, according to the selected consumption curve;
  • Evenly over a specified period — distributes planned values evenly over a user-defined period;
  • Proportionally to physical volume — distributes planned cost and labor units in proportion to planned physical volume values for the working period.

Attention! This distribution scenario is available when “Cost” and “Labor units” are selected. Values are calculated using the following formulas:

  • Operational plan (labor units) = Operational plan (physical volume) × Labor constant;
  • Approved plan (labor units) = Approved plan (physical volume) × Labor constant;
  • Operational plan (cost) = Operational plan (physical volume) × Rate;
  • Approved plan (cost) = Approved plan (physical volume) × Rate.

register imageConfiguring daily distribution of planned activity values in simplified planning

Actual values are distributed over a period beginning on the working day after the date of the last recorded actual value. Select the distribution end date, which is excluded from the period, using one of the following options (1):

  • Schedule version update date;
  • Current date;
  • User-defined date.

After selecting an option, click “Apply” (2).

register imageConfiguring daily distribution of actual activity values

The daily plan distribution results appear both on the right side of the “Schedule” screen (1) and in the working area (2). Activity periods after the current date are highlighted in green; other activity periods are highlighted in light blue. Cells for days when the activity is not performed remain uncolored.

register imageDaily plan distribution results in Simplified planning mode

To copy a daily plan, select the required activity using its checkbox (1), click “Services” (2), and select “Copy daily plan” (3). In the window that opens, select the copy mode (4):

  • “Copy Operational plan to Approved plan” — copies operational planned values to the approved plan;
  • “Copy Approved plan to Operational plan” — copies approved planned values to the operational plan.

Next, select the items to copy (5), specify the period within which values will be copied (6), and click “Apply” (7).

register imageCopying a daily plan in Simplified planning mode

To clear daily planned or actual data in bulk, select the activities whose data you want to clear using their checkboxes (1), click “Services” (2), and select “Delete distribution” (3). In the window that opens, select the daily distribution type (4), data type (5), and period to clear (6), then click “Delete” (7).

register imageClearing daily planned and actual data in Simplified planning mode