SCHEDULE INTERFACE

The left side of the Schedule view displays the Work Breakdown Structure, consisting of structural nodes (work packages) and activities. The Gantt chart is on the right. The following tabs are available at the bottom:

  • Activity card (1);
  • Activity links (2);
  • Linked schedules (3);
  • Directories (4);
  • Resource planning (5);
  • Checklists (6);
  • Photos/documentation (7);
  • Requests and assignments (8).

Schedule view controls (9) are located at the top and in the left-side menu. Click "Schedule information" (10) to view the schedule name, status, update date, and full path in the Enterprise Project Structure. You can also see users currently working in the schedule in real time (11).

register imageSchedule View

Additional interface controls allow you to hide:

  • The WBS area (1);
  • The Gantt chart (2);
  • The workspace (3).

register imageAdditional Schedule Interface Settings

Gantt Chart

The Gantt chart (1), on the right side of the Schedule view, displays:

  • Activities and milestones with dates from the open schedule version (2);
  • Work packages with dates from the open version (3);
  • Dependencies between activities (4);
  • Activities and milestones with dates from the Baseline version (5);
  • Work packages with dates from the Baseline version (6);
  • The schedule update date as a red dashed vertical line (7);
  • The current date as a blue dashed vertical line (8);
  • Project indicators (9).

register imageGantt Chart

Activities on the critical path are shown in red. The critical path is recalculated when the schedule is calculated. Activity progress is shown in blue. Activities with no progress are green.

To scroll horizontally, hold the left mouse button on the timeline and drag in the required direction. To zoom, scroll the mouse wheel over the timeline or use the zoom buttons.

Adjusting the Gantt Chart Scale

Click "Chart parameters" (1). Select a time range: year, quarter, month, week, or day (2). For example, selecting Month displays the month containing the selected activity. Select the time-scale interval: year, quarter, month, week, day, or hour (3). For example, selecting Day divides the lower timeline row into individual days. The chart automatically centers on the selected activity, or on the current date if no activity is selected.

Select automatic scaling to visible activities (4) to fit all currently displayed activities within the chart. The scale adjusts automatically as the displayed activities change. Select "Follow the selected activity" (5) and configure its display parameters (6) to scale the chart to the selected activity. You can also use the calendar (6) to specify a custom interval.

register imageAdjusting the Gantt Chart Scale

Click "Show/Hide saw" (1) to control the progress line, called the Saw in PLAN-R. The Saw is a vertical or jagged red line connecting actual progress points across activities for the date specified in its settings. It helps assess whether activities are on schedule (2). If all activities are on schedule, the line is straight and vertical. Deviations make it jagged, with peaks identifying activities requiring further analysis and monitoring.

register imageDisplaying the Saw on the Gantt Chart

Configuring the Saw Display

Click "Setting up lines" (1), open "Progress" (2), select the line to configure (3), and choose the percentage to display (4). Click "Save" (5).

register imageConfiguring the Saw Display

To configure the Saw relative to the target or current date, open "Saw settings" (1) and adjust its display parameters (2).

register imageSaw Settings

Network Diagram

Open "Network diagrams" (1). The diagram displays activity cards for activities selected using checkboxes (2). To change card size, open settings (3) and specify the display parameters (4). Cards contain attributes added to the WBS (5).

Activity links are shown within each node.

register imageNetwork Diagram

When "Map mode" (1) is selected and "Sections" (2) is empty, you can zoom using the mouse wheel. Adjust the diagram display by hiding the WBS area (3), hiding the workspace (4), or resizing the areas (5).

register imageConfiguring the Network Diagram Display

A selected activity card has a black border (1), and the corresponding activity is highlighted in the WBS (2).

Card colors indicate status:

  • Green — Not started (3);
  • Blue — Completed (4);
  • Gradient — In progress (5).

register imageActivity Cards in the Network Diagram

Clicking an activity highlights all its incoming and outgoing links (1). To create a link quickly, select an activity (2), press F2, and select the other activity. For additional shortcuts, see Annex 5. Keyboard Shortcuts in PLAN-R. PLAN-R creates a Finish-to-Start link with zero lag. You can change the link type or lag on the "Activity links" tab at the bottom of the Schedule view.

Critical-path activity cards use the color configured in the view's line color scheme (3), red by default. A red line connects two linked activities on the critical path (4).

If an activity's Free Float (5) is greater than zero, links to all its successors are dashed (6).

register imageLinks in the Network Diagram

Network diagram line colors are shown in the table below.

Network Diagram Line Colors

Color Line Type Meaning
Solid Critical-path link for a selected activity
Solid Link for a selected activity without free float
Dashed Link for a selected activity with free float
Solid Critical-path link for an unselected activity
Solid Link for an unselected activity without free float
Dashed Link for an unselected activity with free float

To filter by driving predecessors, click "Show local activity chains" (1). Selecting an activity (2) then displays predecessor chains whose activities have Free Float less than or equal to zero. A chain stops when it reaches an activity with positive Free Float.

register imageFiltering the Network Diagram by Driving Predecessors

To display a grouped network diagram, disable "Map mode" (1). Activity links are displayed separately within each node. Grouping colors match the view applied to the WBS (2). To organize the diagram into sections, select the attribute used to distribute activity cards (3). Its values appear at the top of the diagram (4).

register imageGrouped Network Diagram

Activity Card

Left-click an activity or work package (schedule structure node) (1) to view its details on "Activity card" (2). The card displays available attribute values, physical volumes, Controlling Resources, planned and actual values, the assigned calendar, and the schedule calculation scenario.

register imageActivity / Node Card

To display activity types in the schedule, add the Type attribute through view settings (1). The activity icon changes automatically according to the type selected in its card (1).

Set activity status in the WBS or in the card's Status field (2). The system attribute supports:

  • Not started;
  • In progress;
  • Completed.

Status allows an activity to start with zero progress or remain incomplete at 100%.

Changing Progress updates Status as follows:

Changing Activity Status Through Progress

Progress Attribute Value Status Attribute Value
if 100 then Completed
if > 0 and <100 then In progress
if 0 then Not started

Use the Start and Finish drop-down fields (3) to set constraints: No later than, No earlier than, or On date. Start and finish constraints can be applied simultaneously.

To create a variable-duration hammock activity, enable "Start as early as possible" and "Finish as late as possible" (4). The activity starts on its early date and finishes on its late date. These properties are displayed in In range (5).

If both options are enabled, In range is set to Stretch, and the activity has a wavy appearance on the Gantt chart (6).

If both options are disabled, the activity retains its dates during schedule calculation and is not moved to early or late dates.

This functionality supports planning background activities. If a hammock activity becomes critical or has no links, it becomes a regular activity whose work duration equals its initial duration.

The Initial duration system attribute supports more accurate forecast finish calculations for started activities, hammock activities, and date constraints.

register imageActivity / Node Card Settings

You can assign physical volume and a Controlling Resource in the Activity card. See Simplified Planning for physical volume and Resource Planning Schedule Structure for Controlling Resources.

Collapsing and Expanding Nodes

PLAN-R provides the following WBS navigation options:

  • Go to the beginning of the schedule (1);
  • Go to the end of the schedule (2);
  • Collapse all (3);
  • Expand all (4);
  • Collapse to a selected level from 1 to x (5).

Keyboard shortcuts are provided in Annex 5. Keyboard Shortcuts in PLAN-R.

Separate buttons select all checkboxes (6) or clear them (7).

register imageWork Breakdown Structure

Filtering

To display only specific activities, select their checkboxes (1), click "System filters" (2), and select "Show only selected" (3). Select the same option again to remove this filter.

register imageFiltering Activities by Checkboxes

To filter by any attribute, right-click its name in the WBS. PLAN-R provides filter types appropriate to its data type. Select the filter type (1) and parameters (2) to display matching activities.

Clear "Select all" (3) and select the values to display (4). After applying the filter (5), a filter icon appears next to the attribute name (6). Click it to edit or reset the filter (7).

Resize the filter dialog by dragging its edges. Move it by dragging its title. Click "Close" (8) or outside the dialog to close it.

Available filters depend on the attribute type:

  • String and Cross-version: Contains, Does not contain, Empty, Not empty, Equal to, Not equal to.
  • Date: Equal to, Greater than, Less than, Between, Empty, Not empty.
  • Number: Greater than, Greater than or equal to, Less than, Less than or equal to, Between, Empty, Not empty, Equal to.
  • Indicator: Empty, Not empty, Colors, with selection from available indicator colors.

Filters can be combined across multiple attributes. The toolbar displays the number of filtered entries and total activities (9).

To reset a particular filter, right-click the attribute name with the filter icon and select "Reset" (7). Click "Clear filters" (10) to reset all filters.

register imageFiltering Schedule Activity Attribute Values

Click "Views" to see configured WBS filters in the selected attribute list, marked with red filter icons (1). Click "Save changes" (2) to save them; the icons turn gray (3).

To remove saved filtering settings, reset the WBS filters, open "Views", and click "Save changes".

register imageSaving WBS Filtering Settings

Additional filters are available:

  • Critical path (1) — Activities on the critical path.
  • Filter by acceptance (2) — Activities with accepted or unaccepted estimated data.
  • Filter by member (3) — Activities assigned to a participant or assignee.
  • Filter by execution status (4) — Not started, In progress, or Completed activities.

register imageAdvanced Activity Filtering

Sorting

Left-click an attribute name in the current view (1):

  • First click: ascending order;
  • Second click: descending order;
  • Third click: reset sorting.

PLAN-R supports multilevel sorting. Each additional sort preserves the ordering established by previous attributes. There is no limit to the number of sorting attributes. If the WBS is displayed incorrectly, click "Update the structure" (2) to restore the correct order.

register imageSorting Activities by Attribute Values

Click "Views" to see configured sorting in the selected attribute list, marked with red sorting icons (1). Click "Save changes" (2) to save it; the icons turn gray (3).

To remove saved sorting settings, reset WBS sorting, open "Views", and click "Save changes".

register imageSaving WBS Sorting Settings

Grouping Activities

Click "Grouping" (1) to select an existing grouping or open its settings (2).

register imageGrouping Activities

The "Grouping settings" dialog lists existing configurations on the left (1). Click "+Add" (2), enter a name (3), and move the grouping attributes to the area on the right (4). Click "Save" (5) and close the dialog (7). Select "Global" (6), if needed, to make the grouping available to other users of this schedule version.

register imageGrouping Settings (1)

To group activities by assigned resources, open "By resources" (1), select a resource directory (2), and click "Save" (3).

register imageGrouping Settings (2)

To apply a grouping, click "Grouping" and select it. The schedule updates automatically using the selected parameters (3). The active grouping name is shown in light gray.

register imageApplying Grouping to a Schedule

Configuring Views (Layouts)

Drag the dividing boundaries to resize interface areas and activity attribute columns. Sizes are saved for the active view together with the workspace tab active when the view is saved.

To display activities without WBS nodes, click "Grouping" (1) and select "Activities only" (2). Select "Nodes only" (3) to display only nodes. Views are saved separately for each project schedule and user. Opening any schedule version applies the most recently active view for that schedule.

To configure views, click "View" (4) on the toolbar and select "Settings" (5).

View settings are also available in "View" on the sidebar (4).

register imageOpening View Settings (1)

In "View" (1), select an EPS node (2) and a view from the list (3). Click "Add view" (4) to create a view. "Import from file" (5) imports a .view file containing a PLAN-R schedule view. Click "Activate" (6) to apply a view.

register imageOpening View Settings (2)

You can copy a view to EPS nodes available to you. In "View settings", click "Copy" (1), select destination nodes using checkboxes (2), and click "Copy" (3).

register imageCopying a View to Other Schedules

Adding a New View

Click "+ Add view" (1) and enter a name (2).

In "View settings", select attributes of different types (3). Drag an attribute from "Available fields" (4) to "Selected fields" (5), or double-click it. Remove an attribute by double-clicking it or clicking "×" (6).

Attribute colors help identify their types:

  • Custom and reference: green;
  • List: orange;
  • Calculated: blue.

Select "Global" (7) to make the view available across all schedule versions, including Actual and Baseline, and to all users in the space.

You can freeze columns (8) and configure the minimum number of lines in a cell (9).

Click "Save changes" (10) to save the view. "Save as new view" (11) copies the settings to a new view. Click "Activate" (12) to apply a saved view.

"Import from file" (13) imports a .view file. "Export to file" (14) exports the current view.

To delete a view, select it and click "Delete" (15). Click "Cancel" (16) or close the window (17) to exit.

register imageCreating and Configuring Schedule Views

Additional row-height controls are available:

  • Fit row height to content (1) — Automatically adjusts row height to cell contents.
  • Calculate row heights (2) — Recalculates optimal heights using current data and font settings.
  • Reset row sizes (3) — Restores PLAN-R's default row heights.

register imageManaging Table Row Heights

The "Activity style" dialog (1) configures activity fonts according to conditions. Click "Add" (2) to create a condition. For example, to underline activities whose Progress equals 100, select Progress (3), Equal to (4), and 100 (5). Click the "A" icon (6) to display font controls on the right. Choose the font (7), size (8), and style (9). Select "Strikethrough" (10) or "Underline" (11) if needed, or restore the default font style (12).

You can add multiple conditions (13). Click the trash button (14) to delete one. "Export" (15) saves the activity style as .json. "Import" (16) loads a .json file to apply an existing style. Click "Save" (17).

register imageActivity Style Dialog

The "Grouping color scheme" dialog (1) configures node colors and text at each WBS level for light (2) and dark (3) themes. Select a level and click its color button (4) to change the fill, or the edit button (5) to configure text. Choose colors from the palette (6) or spectrum (7). Configure font (8), size (9), style (10), Strikethrough (11), or Underline (12). You can select Monochrome (13) or restore defaults (14). Preview the selected colors on the WBS diagram on the left (15). "Export" (16) exports a text file with background color codes and text parameters. "Import" (17) imports such a file. If it specifies a color for only one grouping row, other node colors remain unchanged. Click "Save" (18) to save the color scheme and "Save changes" (19) to apply the view settings.

register imageConfiguring the Grouping Color Scheme

Click "Setting up lines" (1) to configure Gantt chart lines. Click "Add line" (2) and enter a name (3). Selecting the checkbox next to the line name makes it the main line (4), used to build links in the WBS and network diagram. Click the eye icon (5) to hide a line. "Default lines" (6) deletes added lines and restores defaults. To delete one line, select it (7) and click "Delete line" (8).

In "Bounds" (9), select the start bound (10) and finish bound (11).

register imageConfiguring Line Bounds

In "Labels" (1), select "Show labels" (2), then choose the attribute to display (3). Select "Show work group labels" (4) to display labels for work groups.

register imageConfiguring Activity Labels

In "Progress" (1), select a percentage attribute (2) used to construct the Saw (see Configuring the Saw Display){target="_self"}.

register imageConfiguring Gantt Chart Percentages

In "Style" (1), configure activity line colors for light (2) and dark (3) themes. Select a color from the palette or spectrum for each element (4), or restore defaults (5). Click "Visibility on the Gantt" (6) to configure element visibility.

register imageLine Color Scheme: General Settings

In "Conditional color" (1), configure activity colors using filters. Click "Add" (2), choose an attribute (3), an operator (4), and a value (5), then select colors for completed (6) or incomplete activities (7). Each condition has a "Visibility on the Gantt" button (8) to enable or disable the rule temporarily without deleting it.

Line settings are saved automatically when the window closes. Click "Save changes" (9) to apply them to the Gantt chart.

register imageLine Color Scheme: Filters

Quick Activation of Saved Views

Click "View" (1) on the schedule toolbar and select the required saved view (2).

register imageActivating Saved Views (1)

You can also activate views from "View" (1) on the left sidebar. The view list displays inheritance within the EPS tree. To configure an inherited view, select its source node (2). The "Inherited" label (3) changes to a trash button. Click "Activate" (4) to apply the view.

register imageActivating Saved Views (2)


608.0-5d1f26c7